DSR 2023 · SH 17 · SANITARY INSTALLATIONS

CPWD DSR item 17.61.3 rate analysis

Cutting chases in brick masonry walls for following diameter sand cast iron/centrifugally cast (spun) iron pipes and making good the same with cement concrete 1:3:6 ( 1 cement : 3 coarse sand :6 graded stone aggregate 12.5 mm nominal size), including necessary plaster and pointing in cement mortar 1:4 (1 cement : 4 coarse sand) : 50 mm dia

Published rate₹336.00DSR 2023
Rate analysis

Cutting chases in brick masonry walls for following diameter sand cast iron/centrifugally cast (spun) iron pipes and making good the same with cement concrete 1:3:6 ( 1 cement : 3 coarse sand :6 graded stone aggregate 12.5 mm nominal size), including necessary plaster and pointing in cement mortar 1:4 (1 cement : 4 coarse sand) :

DSR rate₹336.00as per item analysis

50 mm dia

Item code
17.61.3
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
See analysis
Source row
4087

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one metre
MATERIAL
Cement concrete 1:3:6 (1 cement : 3 coarse sand :6 graded stone aggregate )
4.2.5 Rate as per item no 4.2.5 of SH : Concrete work cum 0.008 ₹9,311.40 ₹74.49
9999 Plastering in cement mortar 1:4 L.S. 5.2 ₹2.27 ₹11.80
9977 Carriage of materials L.S. 2.73 ₹2.27 ₹6.20
LABOUR
0123 Mason 1st class day 0.07 ₹897.00 ₹62.79
0114 Beldar day 0.14 ₹736.00 ₹103.04

Rate build-up

TOTAL ₹258.32
Add 1 % Water charges on "W-A" ₹1.84
TOTAL ₹260.16
Add GST on "X-A" (multiplying factor 0.2127) ₹39.49
TOTAL ₹299.65
Add 15% CPOH on "Y-A" ₹33.77
TOTAL ₹333.42
Add Cess @ 1% on "Z-A" ₹2.59
Cost of one metre ₹336.01
Say ₹336.00

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook