DSR 2023 · SH 17 · SANITARY INSTALLATIONS

CPWD DSR item 17.61.1 rate analysis

Cutting chases in brick masonry walls for following diameter sand cast iron/centrifugally cast (spun) iron pipes and making good the same with cement concrete 1:3:6 ( 1 cement : 3 coarse sand :6 graded stone aggregate 12.5 mm nominal size), including necessary plaster and pointing in cement mortar 1:4 (1 cement : 4 coarse sand) : 100 mm dia

Published rate₹713.20DSR 2023
Rate analysis

Cutting chases in brick masonry walls for following diameter sand cast iron/centrifugally cast (spun) iron pipes and making good the same with cement concrete 1:3:6 ( 1 cement : 3 coarse sand :6 graded stone aggregate 12.5 mm nominal size), including necessary plaster and pointing in cement mortar 1:4 (1 cement : 4 coarse sand) :

DSR rate₹713.20as per item analysis

100 mm dia

Item code
17.61.1
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
See analysis
Source row
4087

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one metre
MATERIAL
Cement concrete 1:3:6 (1 cement : 3 coarse sand :6 graded stone aggregate )
4.2.5 Rate as per item no 4.2.5 of SH : Concrete work cum 0.022 ₹9,311.40 ₹204.85
9999 Plastering in cement mortar 1:4 L.S. 10.4 ₹2.27 ₹23.61
9977 Carriage of materials L.S. 4.16 ₹2.27 ₹9.44
LABOUR
0123 Mason 1st class day 0.14 ₹897.00 ₹125.58
0114 Beldar day 0.27 ₹736.00 ₹198.72

Rate build-up

TOTAL ₹562.20
Add 1 % Water charges on "W-A" ₹3.57
TOTAL ₹565.77
Add GST on "X-A" (multiplying factor 0.2127) ₹76.77
TOTAL ₹642.54
Add 15% CPOH on "Y-A" ₹65.65
TOTAL ₹708.19
Add Cess @ 1% on "Z-A" ₹5.03
Cost of one metre ₹713.22
Say ₹713.20