DSR 2023 · SH 17 · SANITARY INSTALLATIONS

CPWD DSR item 17.56.1.3 rate analysis

Providing and fixing terminal guard : 100 mm Hubless centrifugally cast (spun) iron epoxy coated inside & outside as per IS:15905

Published rate₹427.80DSR 2023
Rate analysis

Providing and fixing terminal guard : 100 mm

DSR rate₹427.80as per item analysis

Hubless centrifugally cast (spun) iron epoxy coated inside & outside as per IS:15905

Item code
17.56.1.3
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
See analysis
Source row
3648

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for one no.
MATERIAL
7641 Hubless centrifugally cast (spun) iron terminal guard (slotted cowl) - 100 mm dia as per IS 15905 each 1 ₹270.00 ₹270.00
9977 Carriage of materials and fixing charges L.S. 13.52 ₹2.27 ₹30.69

Rate build-up

TOTAL ₹300.69
Add 1 % Water charges on "W" ₹3.01
TOTAL ₹303.70
Add GST on "X" (multiplying factor 0.2127) ₹64.60
TOTAL ₹368.30
Add 15% CPOH on "Y" ₹55.25
TOTAL ₹423.55
Add Cess @ 1% on "Z" ₹4.24
Cost of each ₹427.79
Say ₹427.80

Use this rate in the interactive workbook