Rate analysis
Providing and fixing door piece, insertion rubber washer 3mm thick, bolts & nuts complete : 75 mm
DSR rate₹537.00as per item analysis
Sand cast iron S&S as per IS - 3989
- Item code
- 17.55.2.2
- Sub-head
- SH 17 · SANITARY INSTALLATIONS
- Unit
- See analysis
- Source row
- 3573
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for one no. | |||||
| MATERIAL | |||||
| 3729 | S.C.I. S&S door pieces 75 mm dia | each | 1 | ₹335.00 | ₹335.00 |
| 1373 | Rubber insertions for 80 mm dia pipe joints | each | 1 | ₹18.00 | ₹18.00 |
| 9988 | Carriage of materials and fixing charges | L.S. | 10.79 | ₹2.27 | ₹24.49 |
Rate build-up
| TOTAL | ₹377.49 |
| Add 1 % Water charges on "W" | ₹3.77 |
| TOTAL | ₹381.26 |
| Add GST on "X" (multiplying factor 0.2127) | ₹81.09 |
| TOTAL | ₹462.35 |
| Add 15% CPOH on "Y" | ₹69.35 |
| TOTAL | ₹531.70 |
| Add Cess @ 1% on "Z" | ₹5.32 |
| Cost of each | ₹537.02 |