DSR 2023 · SH 17 · SANITARY INSTALLATIONS

CPWD DSR item 17.53A.1.2 rate analysis

Providing and fixing Hubless centrifugally cast iron offsets epoxy coated inside & outside as per IS:15905 65 mm offsets With 75 mm dia pipe

Published rate₹454.50DSR 2023
Rate analysis

Providing and fixing Hubless centrifugally cast iron offsets epoxy coated inside & outside as per IS:15905 65 mm offsets

DSR rate₹454.50as per item analysis

With 75 mm dia pipe

Item code
17.53A.1.2
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
See analysis
Source row
3447

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for one no.
MATERIAL
7636 Hubless centrifugally cast (spun) iron 65 mm offset with 75 mm dia pipe as per IS 15905 each 1 ₹295.00 ₹295.00
9977 Carriage of materials and fixing charges L.S. 10.79 ₹2.27 ₹24.49

Rate build-up

TOTAL ₹319.49
Add 1 % Water charges on "W" ₹3.19
TOTAL ₹322.68
Add GST on "X" (multiplying factor 0.2127) ₹68.63
TOTAL ₹391.31
Add 15% CPOH on "Y" ₹58.70
TOTAL ₹450.01
Add Cess @ 1% on "Z" ₹4.50
Cost of each ₹454.51
Say ₹454.50