CPWD DSR item 17.45.1.2 rate analysis

Providing and fixing double unequal junction of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete: 100x100x75x75 mm Sand cast iron S&S as per IS - 3989

Published rate₹1,601.45DSR 2023
Rate analysis

Providing and fixing double unequal junction of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete: 100x100x75x75 mm

DSR rate₹1,601.45as per item analysis

Sand cast iron S&S as per IS - 3989

Item code
17.45.1.2
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
See analysis
Source row
2877

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one no.
MATERIAL
3674 S.C.I. S&S double unequal junctions with access door 100x100x75x75 mm each 1 ₹1,075.00 ₹1,075.00
1374 Rubber insertions for 100 mm dia pipe joints each 1 ₹20.00 ₹20.00
9988 Carriage of materials and fixing charges L.S. 13.52 ₹2.27 ₹30.69

Rate build-up

TOTAL ₹1,125.69
Add 1 % Water charges on "W" ₹11.26
TOTAL ₹1,136.95
Add GST on "X" (multiplying factor 0.2127) ₹241.83
TOTAL ₹1,378.78
Add 15% CPOH on "Y" ₹206.82
TOTAL ₹1,585.60
Add Cess @ 1% on "Z" ₹15.86
Cost of each ₹1,601.46
Say ₹1,601.45