DSR 2023 · SH 17 · SANITARY INSTALLATIONS

CPWD DSR item 17.38.1.2 rate analysis

Providing and fixing bend of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete. 100 mm dia Sand cast iron S&S as per IS - 3989

Published rate₹705.20DSR 2023
Rate analysis

Providing and fixing bend of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete. 100 mm dia

DSR rate₹705.20as per item analysis

Sand cast iron S&S as per IS - 3989

Item code
17.38.1.2
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
See analysis
Source row
2230

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one no.
MATERIAL
3624 S.C.I. S&S bends with access door 100mm dia each 1 ₹445.00 ₹445.00
1374 Rubber insertions for 100 mm dia pipe joints each 1 ₹20.00 ₹20.00
9988 Carriage of materials and fixing charges L.S. 13.52 ₹2.27 ₹30.69

Rate build-up

TOTAL ₹495.69
Add 1 % Water charges on "W" ₹4.96
TOTAL ₹500.65
Add GST on "X" (multiplying factor 0.2127) ₹106.49
TOTAL ₹607.14
Add 15% CPOH on "Y" ₹91.07
TOTAL ₹698.21
Add Cess @ 1% on "Z" ₹6.98
Cost of each ₹705.19