DSR 2023 · SH 17 · SANITARY INSTALLATIONS

CPWD DSR item 17.37.2 rate analysis

Providing and fixing M.S. holder-bat clamps of approved design to Sand Cast iron/cast iron (spun) pipe embedded in and including cement concrete blocks 10x10x10 cm of 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), including cost of cutting holes and making good the walls etc. : For 75 mm dia pipe

Published rate₹360.00DSR 2023
Rate analysis

Providing and fixing M.S. holder-bat clamps of approved design to Sand Cast iron/cast iron (spun) pipe embedded in and including cement concrete blocks 10x10x10 cm of 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), including cost of cutting holes and making good the walls etc. :

DSR rate₹360.00as per item analysis

For 75 mm dia pipe

Item code
17.37.2
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
See analysis
Source row
2149

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 50 nos.
MATERIAL
1332 M.S.Holder bat clamp of approved design for75 mm S.C.I. pipe each 50 ₹25.00 ₹1,250.00
9977 Carriage of bat clamps L.S. 24.7 ₹2.27 ₹56.07
LABOUR
0116 Fitter (grade 1) day 1.25 ₹897.00 ₹1,121.25
0124 Mason 2nd class day 7.5 ₹816.00 ₹6,120.00
0114 Beldar day 5 ₹736.00 ₹3,680.00
9999 Sundries L.S. 71.5 ₹2.27 ₹162.31
C.C. Black 50x0.1x0.1x0.1 = 0.05 cum
0295 Stone Aggregate (Single size) : 20 mm nominal size cum 0.033 ₹1,425.00 ₹47.03
0297 Stone Aggregate (Single size) : 10 mm nominal size cum 0.011 ₹1,400.00 ₹15.40
2202 Carriage of Stone aggregate below 40 mm nominal size cum 0.044 ₹0.00 ₹0.00
0982 Coarse sand (zone III) cum 0.022 ₹1,450.00 ₹31.90
2203 Carriage of Coarse sand cum 0.022 ₹0.00 ₹0.00
0367 Portland Cement (OPC-43 grade) tonne 0.016 ₹5,156.00 ₹82.50
2209 Carriage of Cement tonne 0.016 ₹0.00 ₹0.00
0114 Beldar day 0.045 ₹736.00 ₹33.12
0115 Coolie day 0.032 ₹736.00 ₹23.55
0101 Bhisti day 0.014 ₹816.00 ₹11.42
0123 Mason 1st class day 0.003 ₹897.00 ₹2.69
0124 Mason 2nd class day 0.003 ₹816.00 ₹2.45
0128 Mate day 0.002 ₹816.00 ₹1.63
9999 Hire charges of machine etc. L.S. 2.6 ₹2.27 ₹5.90
9999 Sundries L.S. 1.3 ₹2.27 ₹2.95
9999 Sundries L.S. 1.3 ₹2.27 ₹2.95

Rate build-up

TOTAL ₹12,653.12
Add 1 % Water charges on "W" ₹126.53
TOTAL ₹12,779.65
Add GST on "X" (multiplying factor 0.2127) ₹2,718.23
TOTAL ₹15,497.88
Add 15% CPOH on "Y" ₹2,324.68
TOTAL ₹17,822.56
Add Cess @ 1% on "Z" ₹178.23
Cost of 50 bat clamps ₹18,000.79
Cost of each ₹360.02
Say ₹360.00