DSR 2023 · SH 17 · SANITARY INSTALLATIONS

CPWD DSR item 17.24 rate analysis

Providing and fixing white vitreous china squatting plate urinal with integral rim longitudinal flush pipe.

Published rate₹4,048.65DSR 2023
Rate analysis

Providing and fixing white vitreous china squatting plate urinal with integral rim longitudinal flush pipe.

DSR rate₹4,048.65as per item analysis
Item code
17.24
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
See analysis
Source row
1465

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one no.
MATERIAL
1915 Vitreous china squatting plate urinal each 1 ₹1,158.00 ₹1,158.00
9999 Cement, sand and grit etc. L.S. 10.79 ₹2.27 ₹24.49
9977 Carriage of materials L.S. 13.39 ₹2.27 ₹30.40
LABOUR
0116 Fitter (grade 1) day 0.5 ₹897.00 ₹448.50
0123 Mason 1st class day 0.5 ₹897.00 ₹448.50
0114 Beldar day 1 ₹736.00 ₹736.00

Rate build-up

TOTAL ₹2,845.89
Add 1 % Water charges on "W" ₹28.46
TOTAL ₹2,874.35
Add GST on "X" (multiplying factor 0.2127) ₹611.37
TOTAL ₹3,485.72
Add 15% CPOH on "Y" ₹522.86
TOTAL ₹4,008.58
Add Cess @ 1% on "Z" ₹40.09
Cost of each ₹4,048.67
Say ₹4,048.65