DSR 2023 · SH 17 · SANITARY INSTALLATIONS

CPWD DSR item 17.17.2 rate analysis

Providing and fixing a pair of white vitreous china foot rests of standard pattern for squatting pan water closet : 250x125x25 mm

Published rate₹256.25DSR 2023
Rate analysis

Providing and fixing a pair of white vitreous china foot rests of standard pattern for squatting pan water closet :

DSR rate₹256.25as per item analysis

250x125x25 mm

Item code
17.17.2
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
See analysis
Source row
1217

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one pair
MATERIAL
1970 Vitreous china foot rests 250x125x25 mm pair 1 ₹108.00 ₹108.00
9988 Cement, sand including carriage of materials L.S. 8.06 ₹2.27 ₹18.30
LABOUR
0123 Mason 1st class day 0.06 ₹897.00 ₹53.82

Rate build-up

TOTAL ₹180.12
Add 1 % Water charges on "W" ₹1.80
TOTAL ₹181.92
Add GST on "X" (multiplying factor 0.2127) ₹38.69
TOTAL ₹220.61
Add 15% CPOH on "Y" ₹33.09
TOTAL ₹253.70
Add Cess @ 1% on "Z" ₹2.54
Cost for 1 pair ₹256.24
Say ₹256.25