DSR 2023 · SH 17 · SANITARY INSTALLATIONS

CPWD DSR item 17.12.1 rate analysis

Providing and fixing draining board with C.I. brackets including painting of brackets, cutting and making good the walls wherever required : White glazed fire clay draining board of size 600x450x 25 mm

Published rate₹1,579.65DSR 2023
Rate analysis

Providing and fixing draining board with C.I. brackets including painting of brackets, cutting and making good the walls wherever required :

DSR rate₹1,579.65as per item analysis

White glazed fire clay draining board of size 600x450x 25 mm

Item code
17.12.1
Sub-head
SH 17 · SANITARY INSTALLATIONS
Unit
See analysis
Source row
1072

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one no.
MATERIAL
7364 White glazed fire clay draining board 600x450x25 mm each 1 ₹540.00 ₹540.00
1309 C.I. bracket for wash basin and sinks pair 1 ₹95.00 ₹95.00
9999 Cement, sand and grit etc. L.S. 13.39 ₹2.27 ₹30.40
9999 Painting brackets etc. L.S. 26 ₹2.27 ₹59.02
9977 Carriage of materials L.S. 7.8 ₹2.27 ₹17.71
LABOUR
0116 Fitter (grade 1) day 0.06 ₹897.00 ₹53.82
0123 Mason 1st class day 0.17 ₹897.00 ₹152.49
0114 Beldar day 0.22 ₹736.00 ₹161.92

Rate build-up

TOTAL ₹1,110.36
Add 1 % Water charges on "W" ₹11.10
TOTAL ₹1,121.46
Add GST on "X" (multiplying factor 0.2127) ₹238.53
TOTAL ₹1,359.99
Add 15% CPOH on "Y" ₹204.00
TOTAL ₹1,563.99
Add Cess @ 1% on "Z" ₹15.64
Cost of each ₹1,579.63
Say ₹1,579.65

Use this rate in the interactive workbook