DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.96 rate analysis

Providing & making Gabion structure with Mechanically Woven Double Twisted Hexagonal Shaped Wire mesh Gabion Boxes as per IS 16014:2012,MORTH Clause 2500, of required size, Mesh Type 10x12(D=100 mm with tolerance of ±2%), Zinic+10% Al alloy+PVC coated, Mesh wire diameter 2.7/3.7mm (ID/OD), mechanically edged/selvedged with partitions at every 1m interval and shall have minimum 10 numbers of openings per meter of mesh perpendicular to twist, tying with lacing wire of diameter 2.2/3.2mm(ID/OD), supplied @3% by weight of Gabion boxes, filled with boulders with least dimension of 200 mm, as per drawing, all complete as per directions of Engineer-in-charge.

Published rate₹4,882.20per cum
Rate analysis

Providing & making Gabion structure with Mechanically Woven Double Twisted Hexagonal Shaped Wire mesh Gabion Boxes as per IS 16014:2012,MORTH Clause 2500, of required size, Mesh Type 10x12(D=100 mm with tolerance of ±2%), Zinic+10% Al alloy+PVC coated, Mesh wire diameter 2.7/3.7mm (ID/OD), mechanically edged/selvedged with partitions at every 1m interval and shall have minimum 10 numbers of openings per meter of mesh perpendicular to twist, tying with lacing wire of diameter 2.2/3.2mm(ID/OD), supplied @3% by weight of Gabion boxes, filled with boulders with least dimension of 200 mm, as per drawing, all complete as per directions of Engineer-in-charge.

DSR rate₹4,882.20per cum
Item code
16.96
Sub-head
SH 16 · ROAD WORK
Unit
cum
Source row
5512

Cost components

CodeDescriptionUnitQuantityRateAmount
Details cost of one Gabion box/Crates of size 2mx1mx1m = 2 cum
MATERIAL
8578 Crates made of Mesh type 10x12 (D=100 mm) Zn+10% Al alloy + PVC coated. Mesh wire diameter 2.70/3.70 mm (ID/OD). sqm 11 ₹320.00 ₹3,520.00
Surface area required = 11.00 sqm.
7753 Stone boulder with least dimension 200mm cum 2 ₹875.00 ₹1,750.00
LABOUR
0128 Mate day 0.1 ₹816.00 ₹81.60
0125 Mason (for plain stone work) 2nd class day 0.5 ₹816.00 ₹408.00
0114 Beldar day 1.5 ₹736.00 ₹1,104.00

Rate build-up

TOTAL ₹6,863.60
Add 1 % Water charges on "W" ₹68.64
TOTAL ₹6,932.24
Add GST on "X" (multiplying factor 0.2127) ₹1,474.49
TOTAL ₹8,406.73
Add 15% CPOH on "Y" ₹1,261.01
TOTAL ₹9,667.74
Add Cess @ 1% on "Z" ₹96.68
Cost of 2 cum ₹9,764.42
Cost of 1 cum ₹4,882.21
Say ₹4,882.20

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook