Rate analysis
Laying at or near ground level old kerb stones of all types in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement : 3 coarse sand), including making joints with or without grooves (thickness of joints, except at sharp curve, shall not be more than 5 mm), including making drainage opening wherever required etc. complete as per direction of Engineer-in-charge. (Length of finished kerb edging shall be measured for payment). (Old kerb stones shall be supplied by the department free of cost)
DSR rate₹109.45per meter
- Item code
- 16.85
- Sub-head
- SH 16 · ROAD WORK
- Unit
- meter
- Source row
- 5173
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 100 meter. | |||||
| MATERIAL | |||||
| Number of kerb stones = 100 / 0.405= 247 Nos. | |||||
| Qty. = 247 x 0.40 x 0.375 x 0.20 = 7.41cum | |||||
| No. of joints = 247 - 1 = 246 Nos. | |||||
| Cement Mortar 1:3 for fixing joints = 246 x[(0.115 + 0.20)/2 x 0.375 x 0.005] = 0.073 cum | |||||
| 3.8 | Rate as per Item No.3.8 of SH:MORTARS | cum | 0.073 | ₹4,881.95 | ₹356.38 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 2.5 | ₹897.00 | ₹2,242.50 |
| 0124 | Mason 2nd class | day | 2.5 | ₹816.00 | ₹2,040.00 |
| 0114 | Beldar | day | 2.5 | ₹736.00 | ₹1,840.00 |
| 0115 | Coolie | day | 1.65 | ₹736.00 | ₹1,214.40 |
Rate build-up
| TOTAL | ₹7,693.28 |
| Add 1 % Water charges on "W" | ₹76.93 |
| TOTAL | ₹7,770.21 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,652.72 |
| TOTAL | ₹9,422.93 |
| Add 15% CPOH on "Y" | ₹1,413.44 |
| TOTAL | ₹10,836.37 |
| Add Cess @ 1% on "Z" | ₹108.36 |
| Cost of 100 meter. | ₹10,944.73 |
| Cost of 1 meter. | ₹109.45 |
| Say | ₹109.45 |