CPWD DSR item 16.78.3 rate analysis

Construction of granular sub-base by providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in-Charge. With material conforming to Grade-III (size range 26.5 mm to 0.075 mm ) having CBR Value-20

Published rate₹2,808.55per cum
Rate analysis

Construction of granular sub-base by providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in-Charge.

DSR rate₹2,808.55per cum

With material conforming to Grade-III (size range 26.5 mm to 0.075 mm ) having CBR Value-20

Item code
16.78.3
Sub-head
SH 16 · ROAD WORK
Unit
cum
Source row
4782

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 225 cum (450 tonnes)
MATERIAL
Close graded graunlar sub-base material as per Grading-III of specifications
9.5mm to 4.75mm @ 35% = 100.80 cum
4.75 mm to 2.36mm @ 12.5% = 36.00 cum
2.36mm below @ 52.5% = 151.20 cum
1179 Crushed stone 2.36 mm to 12.5 mm size cum 100.8 ₹1,005.00 ₹1,01,304.00
2202 Carriage of Stone aggregate below 40 mm nominal size cum 100.8 ₹0.00 ₹0.00
1179 Crushed stone 2.36 mm to 12.5 mm size cum 36 ₹1,005.00 ₹36,180.00
2202 Carriage of Stone aggregate below 40 mm nominal size cum 36 ₹0.00 ₹0.00
2903 Stone chippings/ screenings 4.75 mm nominal size cum 75.6 ₹1,600.00 ₹1,20,960.00
2904 Stone chippings/ screenings 150 micron nominal size cum 75.6 ₹1,600.00 ₹1,20,960.00
2203 Carriage of Coarse sand cum 151.2 ₹0.00 ₹0.00
Machinery/ Hire charges:
0059 Wet Mix Plant 60 TPH hour 6 ₹1,050.00 ₹6,300.00
@75 tonne capacity
0070 Generator 100 KVA/125 KVA hour 6 ₹350.00 ₹2,100.00
0057 Water Tanker 5 to 6 KL capacity hour 4.5 ₹250.00 ₹1,125.00
5 km lead with one trip per hour
0052 Front end loader 1 cum bucket capacity (incl POL) hour 6 ₹1,450.00 ₹8,700.00
Tipper 10 tonne capacity( taking lead= 10Km) =450x10 =4500 t.Km
0053 Tipper -5 Cum tonne km 4,500 ₹3.70 ₹16,650.00
Add 10 per cent of cost of carriage to cover cost of loading and unloading ₹1,665.00
0050 Motor Grader 3.35 metre blade hour 6 ₹2,700.00 ₹16,200.00
0054 Vibratory roller 8 to 10 tonne hour 6 ₹700.00 ₹4,200.00
LABOUR
0128 Mate day 0.4 ₹816.00 ₹326.40
0139 Skilled Beldar (for floor rubbing etc.) day 2 ₹816.00 ₹1,632.00
0114 Beldar day 8 ₹736.00 ₹5,888.00

Rate build-up

TOTAL ₹4,44,190.40
Add 1 % Water charges on "W" ₹4,441.90
TOTAL ₹4,48,632.30
Add GST on "X" (multiplying factor 0.2127) ₹95,424.09
TOTAL ₹5,44,056.39
Add 15% CPOH on "Y" ₹81,608.46
TOTAL ₹6,25,664.85
Add Cess @ 1% on "Z" ₹6,256.65
Cost for 225 cum(450 Tonne) ₹6,31,921.50
Cost per cum. ₹2,808.54
Say ₹2,808.55