Rate analysis
Supplying and stacking of hard stone (for stone pitching) 22.5 cm thick at site.
DSR rate₹995.85as per item analysis
- Item code
- 16.72
- Sub-head
- SH 16 · ROAD WORK
- Unit
- See analysis
- Source row
- 4606
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 2.25 cum | |||||
| MATERIAL | |||||
| 22.5 cm thick stone (Hard) | |||||
| 1158 | Stone for pitching 15 cm x 22.5 cm | cum | 2.25 | ₹700.00 | ₹1,575.00 |
| Carriage by mechanical transport i/c loading unloading and stacking | |||||
| 2215 | Carriage of Soling stone & masonary stone | cum | 2.25 | ₹0.00 | ₹0.00 |
Rate build-up
| TOTAL | ₹1,575.00 |
| Add 1 % Water charges on "W" | ₹15.75 |
| TOTAL | ₹1,590.75 |
| Add GST on "X" (multiplying factor 0.2127) | ₹338.35 |
| TOTAL | ₹1,929.10 |
| Add 15% CPOH on "Y" | ₹289.37 |
| TOTAL | ₹2,218.47 |
| Add Cess @ 1% on "Z" | ₹22.18 |
| Cost for 2.25 cum | ₹2,240.65 |
| Cost for one cum | ₹995.84 |
| Say | ₹995.85 |