DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.72 rate analysis

Supplying and stacking of hard stone (for stone pitching) 22.5 cm thick at site.

Published rate₹995.85DSR 2023
Rate analysis

Supplying and stacking of hard stone (for stone pitching) 22.5 cm thick at site.

DSR rate₹995.85as per item analysis
Item code
16.72
Sub-head
SH 16 · ROAD WORK
Unit
See analysis
Source row
4606

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 2.25 cum
MATERIAL
22.5 cm thick stone (Hard)
1158 Stone for pitching 15 cm x 22.5 cm cum 2.25 ₹700.00 ₹1,575.00
Carriage by mechanical transport i/c loading unloading and stacking
2215 Carriage of Soling stone & masonary stone cum 2.25 ₹0.00 ₹0.00

Rate build-up

TOTAL ₹1,575.00
Add 1 % Water charges on "W" ₹15.75
TOTAL ₹1,590.75
Add GST on "X" (multiplying factor 0.2127) ₹338.35
TOTAL ₹1,929.10
Add 15% CPOH on "Y" ₹289.37
TOTAL ₹2,218.47
Add Cess @ 1% on "Z" ₹22.18
Cost for 2.25 cum ₹2,240.65
Cost for one cum ₹995.84
Say ₹995.85

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook