DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.66.1 rate analysis

Excavating holes upto 0.10 cum, including getting out the excavated soil, then returning the soil as deported in layers not exceeding 20 cm in depth, including consolidating and deposited layer by ramming watering etc., disposing of surplus excavated soil as directed with in a lead of 50 mm and lift upto 1.5 m. All kind of soil

Published rate₹27.50per hole
Rate analysis

Excavating holes upto 0.10 cum, including getting out the excavated soil, then returning the soil as deported in layers not exceeding 20 cm in depth, including consolidating and deposited layer by ramming watering etc., disposing of surplus excavated soil as directed with in a lead of 50 mm and lift upto 1.5 m.

DSR rate₹27.50per hole

All kind of soil

Item code
16.66.1
Sub-head
SH 16 · ROAD WORK
Unit
hole
Source row
4427

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 30 holes-
Earth work 30x0.10 = 3.0 cum.
Extra labour for filling and ramming
2.8.1 Rate as per item no. 2.8.1 of SH: Earth work cum 3 ₹260.30 ₹780.90
9999 Sundries L.S. 13.52 ₹2.27 ₹30.69

Rate build-up

TOTAL ₹811.59
Add 1 % Water charges on "W-A" ₹0.31
TOTAL ₹811.90
Add GST on "X-A" (multiplying factor 0.2127) ₹6.59
TOTAL ₹818.49
Add 15% CPOH on "Y-A" ₹5.64
TOTAL ₹824.13
Add Cess @ 1% on "Z-A" ₹0.43
Cost of 30 holes ₹824.56
Cost of 1 hole ₹27.49
Say ₹27.50