DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.57.7 rate analysis

Providing and laying Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge. 40/50 mm compacted thickness with bitumen of grade PMB-40 @ 5.5% (percentage by weight of total mix) and lime filler @ 3% (percentage by weight of Aggregate) prepared in drum Type Hot Mix Plant of 60-90 TPH capacity.

Published rate₹11,104.65per cum
Rate analysis

Providing and laying Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge.

DSR rate₹11,104.65per cum

40/50 mm compacted thickness with bitumen of grade PMB-40 @ 5.5% (percentage by weight of total mix) and lime filler @ 3% (percentage by weight of Aggregate) prepared in drum Type Hot Mix Plant of 60-90 TPH capacity.

Item code
16.57.7
Sub-head
SH 16 · ROAD WORK
Unit
cum
Source row
3617

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 191 cum (450 tonnes)
MATERIAL
0312 Bitumen grade PMB - 40 M.T. 24.75 ₹36,200.00 ₹8,95,950.00
@5.50% (percentage by weight of total mix
2211 Carriage of Tar bitumen tonne 24.75 ₹0.00 ₹0.00
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 24.75 tonnes
Weight of aggregate = 450 -24.75 = 425.25 tonnes
Taking density of aggregate = 1.5 tonne/cum
Volume of aggregate =425.25/1.5 =283.50cum
Grading - II/19 mm (Nominal Size)
13.2 - 10mm size = 30% of 283.50 = 85.05 cum
10 - 5mm size = 25% of 283.50 = 70.88 cum
5mm and below = 42% of 283.50 = 119.07 cum
0296 Stone Aggregate (Single size) : 12.5 mm nominal size cum 42.525 ₹1,400.00 ₹59,535.00
Qty = 85.05 * 50 /100
0297 Stone Aggregate (Single size) : 10 mm nominal size cum 42.525 ₹1,400.00 ₹59,535.00
Qty = 85.05 * 50 /100
0297 Stone Aggregate (Single size) : 10 mm nominal size cum 35.44 ₹1,400.00 ₹49,616.00
Qty = 70.88 * 50 /100
0298 Stone Aggregate (Single size) : 06 mm nominal size cum 35.44 ₹1,425.00 ₹50,502.00
Qty = 70.88 * 50 /100
2903 Stone chippings/ screenings 4.75 mm nominal size cum 119.07 ₹1,600.00 ₹1,90,512.00
Qty = 283.5 * 40 /100
2202 Carriage of Stone aggregate below 40 mm nominal size cum 275 ₹0.00 ₹0.00
Lime Filler @ 2% ( percentage by weight of aggregate)
0777 Dry hydrated lime (factory made) quintal 127.6 ₹315.00 ₹40,194.00
2208 Carriage of Lime cum 9.89 ₹0.00 ₹0.00
(consitering density of lime as 1.29 T per cum) V = 12.758/1.29 = 9.89 cum
MACHINERY/ HIRE CHARGES:
0076 Drum Type HMP of 60-90 TPH capacity @
75 tonne per hour actual output hour 6 ₹13,450.00 ₹80,700.00
0064 Paver finisher Hydrostatic with sensor
control 100 TPH hour 6 ₹1,700.00 ₹10,200.00
0069 Generator 250 KVA hour 6 ₹450.00 ₹2,700.00
0052 Front end loader 1 cum bucket capacity
(incl POL) hour 6 ₹1,450.00 ₹8,700.00
Topper 10 tonne capacity (Taken 10km avarage lead)
450x10=4500 tonne km
0053 Tipper -5 Cum tonne km 4,500 ₹3.70 ₹16,650.00
Add 10 per cent of cost of carriage to cover cost of loading and unloading ₹1,665.00
0055 Smooth Wheeled Roller 8 to 10 tonne hour 3.9 ₹350.00 ₹1,365.00
for initial break down rolling.(6*0.65)
0054 Vibratory roller 8 to 10 tonne hour 3.9 ₹700.00 ₹2,730.00
for intermediate rolling.(6*0.65)
0056 Tandem Road Roller hour 3.9 ₹1,350.00 ₹5,265.00
Finish rolling with 6-8 tonnes smooth wheeled tandem roller.(6*0.65)
LABOUR
0128 Mate day 0.84 ₹816.00 ₹685.44
0114 Beldar day 14 ₹736.00 ₹10,304.00
working with HMP, mechanical broom, paver, roller, asphalt cutter and assistance for setting out lines, levels and layout of construction
0139 Skilled Beldar (for floor rubbing etc.) day 5 ₹816.00 ₹4,080.00
for checking line & levels

Rate build-up

TOTAL ₹14,90,888.44
Add 1 % Water charges on "W" ₹14,908.88
TOTAL ₹15,05,797.32
Add GST on "X" (multiplying factor 0.2127) ₹3,20,283.09
TOTAL ₹18,26,080.41
Add 15% CPOH on "Y" ₹2,73,912.06
TOTAL ₹20,99,992.47
Add Cess @ 1% on "Z" ₹20,999.92
Cost for 191 cum(450 Tonne) ₹21,20,992.39
Cost per cum. ₹11,104.67
Say ₹11,104.65

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook