Rate analysis
Providing and fixing pre-moulded joint filler in expansion joints of RCC roads / CC pavements after making the joints dust free with high pressure air jet cleaners, all complete as per direction of the Engineer-in-Charge. (Pre-moulded joint fillers shall be made of bitumen hot sealing compound impregnated fibre board having impregnation more than 35%, conforming to IS:1838 for fibre board and IS: 1834 for hot sealing bitumen compound grade A.)
DSR rate₹5.30as per item analysis
- Item code
- 16.45
- Sub-head
- SH 16 · ROAD WORK
- Unit
- See analysis
- Source row
- 2826
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 12 mm thick 15cm deep and 300m in length | |||||
| MATERIAL | |||||
| 0317 | Premoulded joint filler board 12 mm thick (Rate inclusive of carriage) = 300x0.15 = 45 sqm. | sqm | 45 | ₹380.00 | ₹17,100.00 |
| Labour for cutting the board in strips, making the joints clean and dust free and fixing etc. : | |||||
| 0112 | Carpenter 2nd class | day | 1 | ₹816.00 | ₹816.00 |
| 0114 | Beldar | day | 3 | ₹736.00 | ₹2,208.00 |
| 9999 | Sundries | L.S. | 26.91 | ₹2.27 | ₹61.09 |
Rate build-up
| TOTAL | ₹20,185.09 |
| Add 1 % Water charges on "W" | ₹201.85 |
| TOTAL | ₹20,386.94 |
| Add GST on "X" (multiplying factor 0.2127) | ₹4,336.30 |
| TOTAL | ₹24,723.24 |
| Add 15% CPOH on "Y" | ₹3,708.49 |
| TOTAL | ₹28,431.73 |
| Add Cess @ 1% on "Z" | ₹284.32 |
| Cost for 300m length, 12mm width and 15cm depth | ₹28,716.05 |
| Cost for one cm. depth one cm. width per metre length. | ₹5.32 |
| Say | ₹5.30 |