2.5 cm premix carpet surfacing with 2.25 cum and 1.12 cum of stone chippings of 13.2 mm and 11.2 mm size respectively per 100 sqm and 52 kg and 56 kg of hot bitumen per cum of stone chippings of 13.2 mm and 11.2 mm size respectively, including a tack coat with hot straight run bitumen, including consolidation with road roller of 6 to 9 tonne capacity etc. complete (tack coat to be paid for separately). With Refinery Modified Bitumen CRMB 55 conforming to IRC: SP: 53

Published rate₹279.90per Sqm
Rate analysis

2.5 cm premix carpet surfacing with 2.25 cum and 1.12 cum of stone chippings of 13.2 mm and 11.2 mm size respectively per 100 sqm and 52 kg and 56 kg of hot bitumen per cum of stone chippings of 13.2 mm and 11.2 mm size respectively, including a tack coat with hot straight run bitumen, including consolidation with road roller of 6 to 9 tonne capacity etc. complete (tack coat to be paid for separately).

DSR rate₹279.90per Sqm

With Refinery Modified Bitumen CRMB 55 conforming to IRC: SP: 53

Item code
16.33.3
Sub-head
SH 16 · ROAD WORK
Unit
Sqm
Source row
1747

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 100 sqm.
MATERIAL
Refinery Modified Bitumen CRMB 55
(i) Hot bitumen @52kg.per cum. of stone chippings @2.25cum. of 13.2mm nominal size chippings.
(ii) Hot bitumen @56kg. per cum. Of aggregate @1.12cum. of 11.2mm nominal size.
52x2.25+56x1.12=180kg
7739 Modified Bitumen Refinary produced CRMB - 55 tonne 0.18 ₹33,100.00 ₹5,958.00
Solvent 0.07x180=12.60kg
2914 Solvent kilogram 12.6 ₹32.00 ₹403.20
2211 Carriage of Tar bitumen tonne 0.18 ₹0.00 ₹0.00
2342 Carriage of solvent/ Diesel. quintal 0.126 ₹0.00 ₹0.00
2910 Stone chippings/ screenings 12.5/ 13.2 mm nominal size cum 2.25 ₹1,400.00 ₹3,150.00
@2.25 cum. per 100sqm
2911 Stone chippings/ screenings 10/ 11.2 mm nominal size cum 1.12 ₹1,400.00 ₹1,568.00
@1.12 cum. per 100sqm
2202 Carriage of Stone aggregate below 40 mm nominal size cum 3.37 ₹0.00 ₹0.00
2.25+1.12=3.37 cum.+
Steam coal for heating of bitumen @2 quintals per tonne of bitumen =2x0.18=0.36q
0370 Coal (steam) quintal 0.36 ₹500.00 ₹180.00
2200 Carriage of steam coal tonne 0.036 ₹0.00 ₹0.00
Labour for cleaning the road surface, heating and spraying bitumen and aggregate :
(a) For cleaning :
0128 Mate day 0.08 ₹816.00 ₹65.28
0114 Beldar day 1.4 ₹736.00 ₹1,030.40
0115 Coolie day 1.4 ₹736.00 ₹1,030.40
(b) For heating bitumen:
0114 Beldar day 0.71 ₹736.00 ₹522.56
(c) For screening and spreading premixed
aggregate :
0130 Mistry day 0.19 ₹897.00 ₹170.43
0114 Beldar day 6.25 ₹736.00 ₹4,600.00
(d) Consolidation Charges
0113 Chowkidar day 0.27 ₹736.00 ₹198.72
0101 Bhisti day 0.11 ₹816.00 ₹89.76
0003 Hire charges of Diesel Road Roller - 8 to 10 tonne day 0.11 ₹3,350.00 ₹368.50
0001 Hire charges of Coaltar Boiler 900 to 1400 litres day 0.15 ₹900.00 ₹135.00
0023 Hot Bitumen mixer 0.5 cum i/c hand cart day 0.04 ₹3,950.00 ₹158.00
(e) Misc:
0364 Wire brush each 0.11 ₹25.00 ₹2.75
(with thick wire)
0365 Soft brush each 0.32 ₹25.00 ₹8.00
9999 Brooms and gunny bags L.S. 6.76 ₹2.27 ₹15.35
9999 Sundries L.S. 9.49 ₹2.27 ₹21.54

Rate build-up

TOTAL ₹19,675.89
Add 1 % Water charges on "W" ₹196.76
TOTAL ₹19,872.65
Add GST on "X" (multiplying factor 0.2127) ₹4,226.91
TOTAL ₹24,099.56
Add 15% CPOH on "Y" ₹3,614.93
TOTAL ₹27,714.49
Add Cess @ 1% on "Z" ₹277.14
Cost for 100 sqm. ₹27,991.63
Cost per Sqm. ₹279.92
Say ₹279.90