DSR 2023 · SH 16 · ROAD WORK

CPWD DSR item 16.31.2.2 rate analysis

Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using emulsion pressure distributer including preparing the surface & cleaning with mechanical broom. With medium setting bitumen emulsion On bituminous surface @ 0.25kg/sqm

Published rate₹14.05per Sqm
Rate analysis

Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using emulsion pressure distributer including preparing the surface & cleaning with mechanical broom. With medium setting bitumen emulsion

DSR rate₹14.05per Sqm

On bituminous surface @ 0.25kg/sqm

Item code
16.31.2.2
Sub-head
SH 16 · ROAD WORK
Unit
Sqm
Source row
1477

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 3500 sqm.
MATERIAL
7742 Bitumen emulsion medium setting (M.S.) confirming to IS : 8887-1995 tonne 0.875 ₹33,530.00 ₹29,338.75
2211 Carriage of Tar bitumen tonne 0.875 ₹0.00 ₹0.00
MACHINERY
0075 Road sweeper (Mechamical Broom) @ 1250 sqm. Per hour. hour 2.8 ₹500.00 ₹1,400.00
0058 Air compressor hour 2.8 ₹250.00 ₹700.00
0061 Emulsion Pressure Distributor @ 1750 sqm per hour hour 2 ₹800.00 ₹1,600.00
LABOUR
0128 Mate day 0.08 ₹816.00 ₹65.28
0114 Beldar day 2 ₹736.00 ₹1,472.00

Rate build-up

TOTAL ₹34,576.03
Add 1 % Water charges on "W" ₹345.76
TOTAL ₹34,921.79
Add GST on "X" (multiplying factor 0.2127) ₹7,427.86
TOTAL ₹42,349.65
Add 15% CPOH on "Y" ₹6,352.45
TOTAL ₹48,702.10
Add Cess @ 1% on "Z" ₹487.02
Cost for 3500 sqm. ₹49,189.12
Cost per Sqm. ₹14.05
Say ₹14.05

Use this rate in the interactive workbook