Rate analysis
Supplying and stacking at site.
DSR rate₹775.50per cum
Good earth
- Item code
- 16.3.9
- Sub-head
- SH 16 · ROAD WORK
- Unit
- cum
- Source row
- 54
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| Excavation : | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.177 | ₹736.00 | ₹130.27 |
| 0115 | Coolie | day | 0.167 | ₹736.00 | ₹122.91 |
| 0979 | Royalty for good earth | cum | 1 | ₹60.00 | ₹60.00 |
| 2241 | Carriage of Good earth | cum | 1 | ₹231.93 | ₹231.93 |
| by mechanical transport upto 5 km lead | |||||
Rate build-up
| TOTAL | ₹545.11 |
| Add 1 % Water charges on "W" | ₹5.45 |
| TOTAL | ₹550.56 |
| Add GST on "X" (multiplying factor 0.2127) | ₹117.10 |
| TOTAL | ₹667.66 |
| Add 15% CPOH on "Y" | ₹100.15 |
| TOTAL | ₹767.81 |
| Add Cess @ 1% on "Z" | ₹7.68 |
| Cost per cum. | ₹775.49 |
| Say | ₹775.50 |