Rate analysis
Providing and fixing 15x15x90 cm boundary stone of hard stone with top 30 cm chisel dressed on all four sides including top (cost of excavation, refilling and concrete etc. to be paid for separately).
DSR rate₹252.90as per item analysis
- Item code
- 16.22
- Sub-head
- SH 16 · ROAD WORK
- Unit
- See analysis
- Source row
- 848
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for one stone | |||||
| 1151 | Boundry stone top chisel dressed 15x15x90 cm | each | 1 | ₹80.00 | ₹80.00 |
| Labour for fixing | |||||
| 0114 | Beldar | day | 0.12 | ₹736.00 | ₹88.32 |
| 9977 | Carriage to site | L.S. | 4.16 | ₹2.27 | ₹9.44 |
Rate build-up
| TOTAL | ₹177.76 |
| Add 1 % Water charges on "W" | ₹1.78 |
| TOTAL | ₹179.54 |
| Add GST on "X" (multiplying factor 0.2127) | ₹38.19 |
| TOTAL | ₹217.73 |
| Add 15% CPOH on "Y" | ₹32.66 |
| TOTAL | ₹250.39 |
| Add Cess @ 1% on "Z" | ₹2.50 |
| Cost of each. | ₹252.89 |
| Say | ₹252.90 |