DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.87 rate analysis

Providing and laying in situ five course water proofing treatment with APP (Atactic Polypropylene) modified Polymeric memberane over roof consisting of first coat of bitumen primer @ 0.40 litre per sqm, 2nd & 4th courses of bonding material @ 1.20 kg/sqm, which shall consist of blown type bitumen of grade 85/25 conforming to IS : 702, 3rd layer of roofing membrane APP modified Polymeric membrane 2.0 mm thick of 3.00 Kg/ sqm weight consisting of five layers prefabricated with centre core as 100 micron HMHDPE film sandwiched on both sides with polymeric mix and the polymeric mix is protected on both side with 20 micron HMHDPE film. 5th, the top most layer shall be finished with brick tiles of class designation 10 grouted with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% integral water proofing compound by weight of cement over a 12 mm layer of cement mortar 1:3 (1 cement : 3 fine sand) and finished neat (item of laying brick tiles shall be paid for separately).

Published rate₹532.05DSR 2023
Rate analysis

Providing and laying in situ five course water proofing treatment with APP (Atactic Polypropylene) modified Polymeric memberane over roof consisting of first coat of bitumen primer @ 0.40 litre per sqm, 2nd & 4th courses of bonding material @ 1.20 kg/sqm, which shall consist of blown type bitumen of grade 85/25 conforming to IS : 702, 3rd layer of roofing membrane APP modified Polymeric membrane 2.0 mm thick of 3.00 Kg/ sqm weight consisting of five layers prefabricated with centre core as 100 micron HMHDPE film sandwiched on both sides with polymeric mix and the polymeric mix is protected on both side with 20 micron HMHDPE film. 5th, the top most layer shall be finished with brick tiles of class designation 10 grouted with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% integral water proofing compound by weight of cement over a 12 mm layer of cement mortar 1:3 (1 cement : 3 fine sand) and finished neat (item of laying brick tiles shall be paid for separately).

DSR rate₹532.05as per item analysis
Item code
14.87
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
See analysis
Source row
2468

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 30 sqm
MATERIAL
APP modified polymeric felt (two layers) 2.0 mm thick = 30 sqm
Add 10% wastage = 3 sqm
Total = 33 sqm
8201 A.P.P. modified polymeric felt (two layers) 2 mm thick sqm 33 ₹130.00 ₹4,290.00
0316 Bitumen solution primer of approved quality litre 12 ₹50.00 ₹600.00
0.4x30 = 12
0313 Blown type petroleum bitumen of penetration 85/25 of approved quality tonne 0.072 ₹38,250.00 ₹2,754.00
1.20x30x2 =72 kg = 0.072 tonne
2211 Carriage of Tar bitumen tonne 0.084 ₹0.00 ₹0.00
9977 Carriage of polymeric felt L.S. 7.8 ₹2.27 ₹17.71
0370 Coal (steam) quintal 0.174 ₹500.00 ₹87.00
2200 Carriage of steam coal tonne 0.017 ₹0.00 ₹0.00
9999 Preparing roof surface, cutting grooves and making good the same L.S. 134.55 ₹2.27 ₹305.43
LABOUR
0131 Painter day 1.58 ₹816.00 ₹1,289.28
0114 Beldar day 2.37 ₹736.00 ₹1,744.32
0130 Mistry day 0.13 ₹897.00 ₹116.61
9999 Sundries, brushes etc L.S. 6.76 ₹2.27 ₹15.35

Rate build-up

TOTAL ₹11,219.70
Add 1 % Water charges on "W" ₹112.20
TOTAL ₹11,331.90
Add GST on "X" (multiplying factor 0.2127) ₹2,410.30
TOTAL ₹13,742.20
Add 15% CPOH on "Y" ₹2,061.33
TOTAL ₹15,803.53
Add Cess @ 1% on "Z" ₹158.04
Cost for 30 sqm ₹15,961.57
Cost for 1 sqm ₹532.05
Say ₹532.05