DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.30.2 rate analysis

Hollock wood

Published rate₹64,022.85per cum
Rate analysis

Hollock wood

DSR rate₹64,022.85per cum
Item code
14.30.2
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
cum
Source row
1443

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 300cudm.
MATERIAL
Hollock wood in scantling
10x0.1mx0.1mx3.0m = 0.30 cum. Or = 300 cudm
Add wastage @ 2% = 6.00 cudm.
Total = 306 cudm.
2466 Hollock wood in scantling 10 cudm 30.6 ₹366.00 ₹11,199.60
2204 Carriage of Timber cum 0.306 ₹0.00 ₹0.00
LABOUR
0112 Carpenter 2nd class day 0.7 ₹816.00 ₹571.20
0114 Beldar day 1.45 ₹736.00 ₹1,067.20
0100 Bandhani day 0.7 ₹816.00 ₹571.20
Priming coat (Wood preservative)
13.57.1 Rate as per item no 13.57.1 SH : Finishing sqm 0.8 ₹54.40 ₹43.52
9999 Sundries L.S. 26.91 ₹2.27 ₹61.09

Rate build-up

TOTAL ₹13,513.81
Add 1 % Water charges on "W-A" ₹134.70
TOTAL ₹13,648.51
Add GST on "X-A" (multiplying factor 0.2127) ₹2,893.78
TOTAL ₹16,542.29
Add 15% CPOH on "Y-A" ₹2,474.82
TOTAL ₹19,017.11
Add Cess @ 1% on "Z-A" ₹189.74
Cost of 300 cudm. ₹19,206.85
Cost of 1 cum. ₹64,022.83
Say ₹64,022.85