Rate analysis
Providing and fixing M.S. round or square bars with M.S. flats at required spacing in wooden frames of windows and clerestory windows.
DSR rate₹120.75per kg
- Item code
- 14.29
- Sub-head
- SH 14 · REPAIRS TO BUILDING
- Unit
- kg
- Source row
- 1378
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 33.67 kg | |||||
| Details of cost for window -140x110cm | |||||
| MATERIAL | |||||
| M.S. bar 16 mm dia 13x136 cm = 17.68 m @ 1.58 kg/m = 27.93 kg | |||||
| Add for wastage @ 10% =2.79 kg | |||||
| Total = 30.72 kg or 0.307 q | |||||
| 1003 | Mild steel round bar above 12 mm dia | quintal | 0.307 | ₹5,450.00 | ₹1,673.15 |
| M.S. flat 40x6mm 2x96cm = 192cm+ | |||||
| 1x110cm = 110cm | |||||
| = 302cm+ | |||||
| Add wastage @ 10% = 30cm | |||||
| Total = 332cm.@ 1.90 kg/m = 6.31 kg | |||||
| 1008 | Flats upto 10 mm in thickness | quintal | 0.063 | ₹5,450.00 | ₹343.35 |
| 2205 | Carriage of Steel | tonne | 0.037 | ₹0.00 | ₹0.00 |
| (0.307+0.063 = 0.37 q = 0.037 t) | |||||
| 9999 | Sundries | L.S. | 26.91 | ₹2.27 | ₹61.09 |
| LABOUR | |||||
| 0103 | Blacksmith 2nd class | day | 0.35 | ₹816.00 | ₹285.60 |
| 0112 | Carpenter 2nd class | day | 0.2 | ₹816.00 | ₹163.20 |
| 0114 | Beldar | day | 0.45 | ₹736.00 | ₹331.20 |
Rate build-up
| Say 0.063 q | — |
| TOTAL | ₹2,857.59 |
| Add 1 % Water charges on "W" | ₹28.58 |
| TOTAL | ₹2,886.17 |
| Add GST on "X" (multiplying factor 0.2127) | ₹613.89 |
| TOTAL | ₹3,500.06 |
| Add 15% CPOH on "Y" | ₹525.01 |
| TOTAL | ₹4,025.07 |
| Add Cess @ 1% on "Z" | ₹40.25 |
| Cost of 33.67 kg.(5.74+27.93=33.67kg) | ₹4,065.32 |
| Cost of 1 kg. | ₹120.74 |
| Say | ₹120.75 |