DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.25 rate analysis

Brick work with common burnt clay bricks of class designation 7.5 in mud mortar

Published rate₹6,207.25per Cum
Rate analysis

Brick work with common burnt clay bricks of class designation 7.5 in mud mortar

DSR rate₹6,207.25per Cum
Item code
14.25
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
Cum
Source row
1093

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
2602 Common burnt clay F.P.S. (non modular) bricks class designation 7.5 1000 Nos 0.494 ₹4,724.00 ₹2,333.66
Mud mortar
3.18 Rate as per Item Number 3.18 of SH: Mortars cum 0.25 ₹940.55 ₹235.14
2201 Carriage of Bricks 1000 Nos 0.494 ₹0.00 ₹0.00
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20
LABOUR
0123 Mason 1st class day 0.36 ₹897.00 ₹322.92
0124 Mason 2nd class day 0.36 ₹816.00 ₹293.76
0115 Coolie day 1.37 ₹736.00 ₹1,008.32
0101 Bhisti day 0.2 ₹816.00 ₹163.20

Rate build-up

TOTAL ₹4,363.20
Add 1 % Water charges on "W" ₹43.63
TOTAL ₹4,406.83
Add GST on "X" (multiplying factor 0.2127) ₹937.33
TOTAL ₹5,344.16
Add 15% CPOH on "Y" ₹801.62
TOTAL ₹6,145.78
Add Cess @ 1% on "Z" ₹61.46
Cost of 1 Cum. ₹6,207.24
Say ₹6,207.25