Rate analysis
Fixing of old wind tie with new fittings including painting two or more coats with anticorrosive bitumastic paint of approved brand & manufacturer over and including priming coat of ready mixed zinc chromate yellow primer of approved brand.
DSR rate₹126.00as per item analysis
- Item code
- 14.2
- Sub-head
- SH 14 · REPAIRS TO BUILDING
- Unit
- See analysis
- Source row
- 903
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 20.2 m wind tie | |||||
| MATERIAL | |||||
| 1023 | Galvanised steel J or L hooks 8 mm dia | 10 Nos | 6.8 | ₹130.00 | ₹884.00 |
| @ 30 cm center to center = 68 Nos | |||||
| 1208 | Bitumen washer | 100 Nos | 0.68 | ₹30.00 | ₹20.40 |
| 1209 | G.I. plain washer thick | 100 Nos | 0.68 | ₹35.00 | ₹23.80 |
| 9977 | Carriage of bolts, nuts and washers etc. | L.S. | 1.17 | ₹2.27 | ₹2.66 |
| LABOUR | |||||
| 0102 | Blacksmith 1st class | day | 0.34 | ₹897.00 | ₹304.98 |
| 0114 | Beldar | day | 0.34 | ₹736.00 | ₹250.24 |
| 9999 | Sundries | L.S. | 13.91 | ₹2.27 | ₹31.58 |
| Applying priming coat with ready mixed zink chromate yellow primer | |||||
| 20.2x2x(0.04+0.006) = 1.86 sqm | |||||
| 13.50.3 | Rate as per item no 13.50.3 of SH : Finishing | sqm | 1.86 | ₹67.40 | ₹125.36 |
| Painting with ready mixed black antcorrosive bitumastic paint | |||||
| 13.65.1 | Rate as per item No.13.65.1 SH: Finishing | sqm | 1.86 | ₹140.25 | ₹260.87 |
Rate build-up
| TOTAL | ₹1,903.89 |
| Add 1 % Water charges on "W-A" | ₹15.18 |
| TOTAL | ₹1,919.07 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹326.04 |
| TOTAL | ₹2,245.11 |
| Add 15% CPOH on "Y-A" | ₹278.83 |
| TOTAL | ₹2,523.94 |
| Add Cess @ 1% on "Z-A" | ₹21.38 |
| Cost of 20.2 metres | ₹2,545.32 |
| Cost of 1.00 metre | ₹126.01 |
| Say | ₹126.00 |