Rate analysis
Raking out joints in lime or cement mortar and preparing the surface for re-pointing or replastering, including disposal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge.
DSR rate₹72.45as per item analysis
- Item code
- 14.17
- Sub-head
- SH 14 · REPAIRS TO BUILDING
- Unit
- See analysis
- Source row
- 810
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 sqm | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.53 | ₹736.00 | ₹390.08 |
| 0115 | Coolie | day | 0.08 | ₹736.00 | ₹58.88 |
| 0101 | Bhisti | day | 0.07 | ₹816.00 | ₹57.12 |
| 9999 | Sundries | L.S. | 1.43 | ₹2.27 | ₹3.25 |
Rate build-up
| TOTAL | ₹509.33 |
| Add 1 % Water charges on "W" | ₹5.09 |
| TOTAL | ₹514.42 |
| Add GST on "X" (multiplying factor 0.2127) | ₹109.42 |
| TOTAL | ₹623.84 |
| Add 15% CPOH on "Y" | ₹93.58 |
| TOTAL | ₹717.42 |
| Add Cess @ 1% on "Z" | ₹7.17 |
| Cost of 10.00 sqm | ₹724.59 |
| Cost of 1.00 sqm | ₹72.46 |