DSR 2023 · SH 14 · REPAIRS TO BUILDING

CPWD DSR item 14.16.1.1 rate analysis

Renewing wooden beams in roofs including making good the holes in walls and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge. Not exceeding 4.00 metres in length. Sal wood beams

Published rate₹1,04,573.95DSR 2023
Rate analysis

Renewing wooden beams in roofs including making good the holes in walls and painting with oil type wood preservative of approved brand and manufacture complete, including removal of rubbish to the dumping ground, all complete as per direction of Engineer-in-Charge. Not exceeding 4.00 metres in length.

DSR rate₹1,04,573.95as per item analysis

Sal wood beams

Item code
14.16.1.1
Sub-head
SH 14 · REPAIRS TO BUILDING
Unit
See analysis
Source row
609

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 3000 cudm or 3 cum
Consider 10 beam i.e. 3000 cudm.
10x0.25 x 0.30m x 4.0m (long) = 3 cum
Add wastage @ 2% (0.06 cum) = 3.06 cum =3060 cudm
(i) Propping the roof
MATERIAL
100x100mm salwood battens 1 metre long = 50 nos.x1.0x0.1x0.1 =0.5cum = 500 cudm.
These materials can be used for 16 times Hence qty for one operation 1/16= 500/16 = 31.25 cudm
1199 Sal wood in scantling 10 cudm 3.125 ₹600.00 ₹1,875.00
2204 Carriage of Timber cum 0.031 ₹0.00 ₹0.00
LABOUR
0112 Carpenter 2nd class day 2.5 ₹816.00 ₹2,040.00
0114 Beldar day 2.5 ₹736.00 ₹1,840.00
(ii) Taking out the existing beams etc.
LABOUR
0155 Mason (average) day 1.3 ₹857.00 ₹1,114.10
0100 Bandhani day 5 ₹816.00 ₹4,080.00
0114 Beldar day 3.3 ₹736.00 ₹2,428.80
(iii) Renewal
Materials and Labour
1199 Sal wood in scantling 10 cudm 306 ₹600.00 ₹1,83,600.00
2204 Carriage of Timber cum 3.06 ₹0.00 ₹0.00
0112 Carpenter 2nd class day 10 ₹816.00 ₹8,160.00
0100 Bandhani day 5 ₹816.00 ₹4,080.00
0114 Beldar day 10 ₹736.00 ₹7,360.00
Painting with oil preservative=
10x[(4x1.1) +( 2.0x0.25x0.30)] = 10x(4.4 + 0.15)= 45.5 sqm @ 1 litre/10sqm = 4.55 litre
0859 Oil type wood preservative litre 4.55 ₹130.00 ₹591.50
0131 Painter day 0.7 ₹816.00 ₹571.20
0115 Coolie day 0.7 ₹736.00 ₹515.20
9999 Sundries L.S. 1.3 ₹2.27 ₹2.95
9977 Carriage L.S. 18.2 ₹2.27 ₹41.31
9999 Brushes L.S. 18.2 ₹2.27 ₹41.31
9999 Making good the holes L.S. 206.7 ₹2.27 ₹469.21
9999 Sundries L.S. 269.1 ₹2.27 ₹610.86
0302 Safeda ballies 125 mm diameter metre 25 ₹44.00 ₹1,100.00

Rate build-up

TOTAL ₹2,20,521.44
Add 1 % Water charges on "W" ₹2,205.21
TOTAL ₹2,22,726.65
Add GST on "X" (multiplying factor 0.2127) ₹47,373.96
TOTAL ₹2,70,100.61
Add 15% CPOH on "Y" ₹40,515.09
TOTAL ₹3,10,615.70
Add Cess @ 1% on "Z" ₹3,106.16
Cost of 3.00 Cum ₹3,13,721.86
Cost of 1.00 cum ₹1,04,573.95
Say ₹1,04,573.95