DSR 2023 · SH 13 · FINISHING

CPWD DSR item 13.74 rate analysis

Extra for washed grit plaster on exterior walls of height more than 10 m from ground level for every additional height of 3 m or part thereof.

Published rate₹165.85DSR 2023
Rate analysis

Extra for washed grit plaster on exterior walls of height more than 10 m from ground level for every additional height of 3 m or part thereof.

DSR rate₹165.85as per item analysis
Item code
13.74
Sub-head
SH 13 · FINISHING
Unit
See analysis
Source row
2604

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
MATERIAL
9999 Scaffolding L.S. 215.28 ₹2.27 ₹488.69
0123 Mason 1st class day 0.3 ₹897.00 ₹269.10
0114 Beldar day 0.3 ₹736.00 ₹220.80
0101 Bhisti day 0.15 ₹816.00 ₹122.40
9999 Sundries L.S. 28.6 ₹2.27 ₹64.92

Rate build-up

TOTAL ₹1,165.91
Add 1 % Water charges on "W" ₹11.66
TOTAL ₹1,177.57
Add GST on "X" (multiplying factor 0.2127) ₹250.47
TOTAL ₹1,428.04
Add 15% CPOH on "Y" ₹214.21
TOTAL ₹1,642.25
Add Cess @ 1% on "Z" ₹16.42
Cost of 10.00 sqm ₹1,658.67
Cost of 1.00 sqm ₹165.87
Say ₹165.85

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook