Rate analysis
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer's specifications including appropriate priming coat, preparation of surface, etc. complete.
DSR rate₹235.15as per item analysis
On concrete work
- Item code
- 13.52.2
- Sub-head
- SH 13 · FINISHING
- Unit
- See analysis
- Source row
- 1844
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 sqm | |||||
| PRIMING COAT | |||||
| MATERIAL | |||||
| 0808 | Water thinnable cement primer for interior wall surface, having VOC content less than 50 grams/ litre | litre | 0.84 | ₹40.00 | ₹33.60 |
| 9999 | Putty | L.S. | 13.52 | ₹2.27 | ₹30.69 |
| 9977 | Carriage | L.S. | 0.52 | ₹2.27 | ₹1.18 |
| LABOUR | |||||
| 0131 | Painter | day | 0.25 | ₹816.00 | ₹204.00 |
| 0115 | Coolie | day | 0.25 | ₹736.00 | ₹184.00 |
| 9999 | Brushes, sand paper etc | L.S. | 2.73 | ₹2.27 | ₹6.20 |
| 9999 | Sundries | L.S. | 8.06 | ₹2.27 | ₹18.30 |
| EPOXY PAINTING | |||||
| MATERIAL | |||||
| 7239 | Epoxy paint | litre | 1.21 | ₹230.00 | ₹278.30 |
| 9999 | Materials for filling in holes and cracks | L.S. | 6.76 | ₹2.27 | ₹15.35 |
| 9977 | Carriage of material | L.S. | 1.43 | ₹2.27 | ₹3.25 |
| LABOUR | |||||
| 0131 | Painter | day | 0.54 | ₹816.00 | ₹440.64 |
| 0115 | Coolie | day | 0.54 | ₹736.00 | ₹397.44 |
| 9999 | Putty, brushes, sand paper etc | L.S. | 10.79 | ₹2.27 | ₹24.49 |
| 9999 | Sundries | L.S. | 6.76 | ₹2.27 | ₹15.35 |
Rate build-up
| TOTAL | ₹1,652.79 |
| Add 1 % Water charges on "W" | ₹16.53 |
| TOTAL | ₹1,669.32 |
| Add GST on "X" (multiplying factor 0.2127) | ₹355.06 |
| TOTAL | ₹2,024.38 |
| Add 15% CPOH on "Y" | ₹303.66 |
| TOTAL | ₹2,328.04 |
| Add Cess @ 1% on "Z" | ₹23.28 |
| Cost of 10.00 sqm | ₹2,351.32 |
| Cost of 1.00 sqm | ₹235.13 |
| Say | ₹235.15 |