DSR 2023 · SH 13 · FINISHING

CPWD DSR item 13.31.2 rate analysis

Pointing on brick work or brick flooring with cement mortar 1:3 (1 cement : 3 fine sand): Raised and cut pointing

Published rate₹419.90DSR 2023
Rate analysis

Pointing on brick work or brick flooring with cement mortar 1:3 (1 cement : 3 fine sand):

DSR rate₹419.90as per item analysis

Raised and cut pointing

Item code
13.31.2
Sub-head
SH 13 · FINISHING
Unit
See analysis
Source row
1205

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
MATERIAL
Cement mortar 1 : 3 (1 cement : 3 fine sand)
3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.046 ₹4,379.05 ₹201.44
LABOUR
0155 Mason (average) day 1.07 ₹857.00 ₹916.99
0115 Coolie day 1.31 ₹736.00 ₹964.16
0101 Bhisti day 1 ₹816.00 ₹816.00
9999 Sundries L.S. 7.15 ₹2.27 ₹16.23
9999 Scaffolding and racking out joints including sundries L.S. 16.12 ₹2.27 ₹36.59

Rate build-up

TOTAL ₹2,951.41
Add 1 % Water charges on "W" ₹29.51
TOTAL ₹2,980.92
Add GST on "X" (multiplying factor 0.2127) ₹634.04
TOTAL ₹3,614.96
Add 15% CPOH on "Y" ₹542.24
TOTAL ₹4,157.20
Add Cess @ 1% on "Z" ₹41.57
Cost of 10.00 sqm ₹4,198.77
Cost of 1.00 sqm ₹419.88
Say ₹419.90

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook