DSR 2023 · SH 13 · FINISHING

CPWD DSR item 13.24.1 rate analysis

Extra for plastering done on moulding, cornices or architraves including neat finish to line and level: In one coat

Published rate₹713.20DSR 2023
Rate analysis

Extra for plastering done on moulding, cornices or architraves including neat finish to line and level:

DSR rate₹713.20as per item analysis

In one coat

Item code
13.24.1
Sub-head
SH 13 · FINISHING
Unit
See analysis
Source row
849

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
LABOUR
0155 Mason (average) day 3 ₹857.00 ₹2,571.00
0114 Beldar day 2 ₹736.00 ₹1,472.00
0115 Coolie day 1 ₹736.00 ₹736.00
0101 Bhisti day 0.25 ₹816.00 ₹204.00
9999 Sundries L.S. 13.39 ₹2.27 ₹30.40

Rate build-up

TOTAL ₹5,013.40
Add 1 % Water charges on "W" ₹50.13
TOTAL ₹5,063.53
Add GST on "X" (multiplying factor 0.2127) ₹1,077.01
TOTAL ₹6,140.54
Add 15% CPOH on "Y" ₹921.08
TOTAL ₹7,061.62
Add Cess @ 1% on "Z" ₹70.62
Cost of 10.00 sqm ₹7,132.24
Cost of 1.00 sqm ₹713.22
Say ₹713.20

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook