DSR 2023 · SH 13 · FINISHING

CPWD DSR item 13.2 rate analysis

Pebble dash plaster upto 10 m height above ground level with a mixture of washed pebble or crushed stone 6 mm to 12.5 mm nominal size, dashed over and including fresh plaster in two layers under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement.

Published rate₹829.95DSR 2023
Rate analysis

Pebble dash plaster upto 10 m height above ground level with a mixture of washed pebble or crushed stone 6 mm to 12.5 mm nominal size, dashed over and including fresh plaster in two layers under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand) and top layer 10 mm cement plaster with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 10% finely grounded hydrated lime by volume of cement.

DSR rate₹829.95as per item analysis
Item code
13.2
Sub-head
SH 13 · FINISHING
Unit
See analysis
Source row
729

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
MATERIAL
Under layer 12 mm thick cement plaster
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.144 ₹4,211.70 ₹606.48
LABOUR
0155 Mason (average) day 0.67 ₹857.00 ₹574.19
0114 Beldar day 0.75 ₹736.00 ₹552.00
0101 Bhisti day 0.92 ₹816.00 ₹750.72
9999 Scaffolding and sundries L.S. 9.88 ₹2.27 ₹22.43
Top layer 10 mm thick cement plaster
Cement mortar 1 : 3 (1 cement : 3 fine sand)
3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.12 ₹4,379.05 ₹525.49
0155 Mason (average) day 0.61 ₹857.00 ₹522.77
0114 Beldar day 0.69 ₹736.00 ₹507.84
0101 Bhisti day 0.85 ₹816.00 ₹693.60
9999 Scaffolding and sundries L.S. 9.88 ₹2.27 ₹22.43
1179 Crushed stone 2.36 mm to 12.5 mm size cum 0.1 ₹1,005.00 ₹100.50
0101 Bhisti day 0.01 ₹816.00 ₹8.16
0777 Dry hydrated lime (factory made) quintal 0.09 ₹315.00 ₹28.35
9977 Carriage of lime L.S. 3.64 ₹2.27 ₹8.26
0155 Mason (average) day 0.5 ₹857.00 ₹428.50
0114 Beldar day 0.5 ₹736.00 ₹368.00
0101 Bhisti day 0.1 ₹816.00 ₹81.60
9999 Scaffolding and sundries L.S. 9.88 ₹2.27 ₹22.43
9999 Scaffolding and sundries L.S. 4.42 ₹2.27 ₹10.03

Rate build-up

TOTAL ₹5,833.78
Add 1 % Water charges on "W" ₹58.34
TOTAL ₹5,892.12
Add GST on "X" (multiplying factor 0.2127) ₹1,253.25
TOTAL ₹7,145.37
Add 15% CPOH on "Y" ₹1,071.81
TOTAL ₹8,217.18
Add Cess @ 1% on "Z" ₹82.17
Cost of 10.00 sqm ₹8,299.35
Cost of 1.00 sqm ₹829.94
Say ₹829.95

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook