Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 10 sqm | |||||
| MATERIAL | |||||
| Cement mortar 1 : 3 (1 cement : 3 fine sand) | |||||
| 3.3 | Rate as per Item Number 3.3 of SH: Mortars | cum | 0.072 | ₹4,379.05 | ₹315.29 |
| LABOUR | |||||
| 0155 | Mason (average) | day | 0.51 | ₹857.00 | ₹437.07 |
| 0115 | Coolie | day | 0.75 | ₹736.00 | ₹552.00 |
| 0101 | Bhisti | day | 0.92 | ₹816.00 | ₹750.72 |
| 9999 | Extra for removing burrs, cleaning with wire brushes, pock making with pointed tool etc. complete. | L.S. | 13.39 | ₹2.27 | ₹30.40 |
| 9999 | Scaffolding and sundries | L.S. | 11.7 | ₹2.27 | ₹26.56 |
| 0367 | Portland Cement (OPC-43 grade) | tonne | 0.02 | ₹5,156.00 | ₹103.12 |
| 2209 | Carriage of Cement | tonne | 0.02 | ₹0.00 | ₹0.00 |
| 0155 | Mason (average) | day | 0.27 | ₹857.00 | ₹231.39 |
| 0115 | Coolie | day | 0.27 | ₹736.00 | ₹198.72 |
| 9999 | Scaffolding and sundries | L.S. | 8.06 | ₹2.27 | ₹18.30 |
| 0776 | Satna lime | quintal | 0.01 | ₹400.00 | ₹4.00 |
| 9999 | Indigo gum etc | L.S. | 2.08 | ₹2.27 | ₹4.72 |
| 9999 | Sundries ladder etc. | L.S. | 0.52 | ₹2.27 | ₹1.18 |
| 0141 | White Washer | day | 0.07 | ₹816.00 | ₹57.12 |
| 0115 | Coolie | day | 0.07 | ₹736.00 | ₹51.52 |
| 9999 | Sundries | L.S. | 2.73 | ₹2.27 | ₹6.20 |
Rate build-up
| TOTAL | ₹2,788.31 |
| Add 1 % Water charges on "W" | ₹27.88 |
| TOTAL | ₹2,816.19 |
| Add GST on "X" (multiplying factor 0.2127) | ₹599.00 |
| TOTAL | ₹3,415.19 |
| Add 15% CPOH on "Y" | ₹512.28 |
| TOTAL | ₹3,927.47 |
| Add Cess @ 1% on "Z" | ₹39.27 |
| Cost of 10.00 sqm | ₹3,966.74 |
| Cost of 1.00 sqm | ₹396.67 |
| Say | ₹396.65 |