DSR 2023 · SH 13 · FINISHING

CPWD DSR item 13.100.1 rate analysis

One or more coats on old work

Published rate₹96.00DSR 2023
Rate analysis

One or more coats on old work

DSR rate₹96.00as per item analysis
Item code
13.100.1
Sub-head
SH 13 · FINISHING
Unit
See analysis
Source row
3412

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 10 sqm
MATERIAL
0826 Aluminium paint litre 0.46 ₹170.00 ₹78.20
9977 Carriage of paint and material L.S. 0.52 ₹2.27 ₹1.18
9999 Putty etc L.S. 2.73 ₹2.27 ₹6.20
LABOUR
0131 Painter day 0.36 ₹816.00 ₹293.76
0115 Coolie day 0.36 ₹736.00 ₹264.96
9999 Brushes, sand paper etc L.S. 5.33 ₹2.27 ₹12.10
9999 Sundries L.S. 8.06 ₹2.27 ₹18.30

Rate build-up

TOTAL ₹674.70
Add 1 % Water charges on "W" ₹6.75
TOTAL ₹681.45
Add GST on "X" (multiplying factor 0.2127) ₹144.94
TOTAL ₹826.39
Add 15% CPOH on "Y" ₹123.96
TOTAL ₹950.35
Add Cess @ 1% on "Z" ₹9.50
Cost of 10.00 sqm ₹959.85
Cost of 1.00 sqm ₹95.99
Say ₹96.00

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook