DSR 2023 · SH 12 · ROOFING

CPWD DSR item 12.66.6 rate analysis

Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete : Precoated/mill finish aluminium Gutter (600 mm over all girth)

Published rate₹1,808.65per metre
Rate analysis

Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete :

DSR rate₹1,808.65per metre

Precoated/mill finish aluminium Gutter (600 mm over all girth)

Item code
12.66.6
Sub-head
SH 12 · ROOFING
Unit
metre
Source row
4007

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost of 100 metre
0.63mm thick with zinc coating not less than 275gm/ sqm
Consider a length of 100m
3073 Precoated/Mill finish Aluminium gutter metre 100 ₹736.00 ₹73,600.00
9977 Carriage of gutter L.S. 10.4 ₹2.27 ₹23.61
1008 Flats upto 10 mm in thickness quintal 0.749 ₹5,450.00 ₹4,082.05
3074 Stainless steel self tapping screw of 6x50mm with SS hex cap and 3mm thick EPDM seal 100 Nos 2 ₹511.00 ₹1,022.00
3076 Stainless steel bolts & nuts 10 mm dia and 125 mm long round head with slots each 300 ₹41.00 ₹12,300.00
9977 Carriage of screws, seam bolts & washer L.S. 27.3 ₹2.27 ₹61.97
9999 Sundries L.S. 53.3 ₹2.27 ₹120.99
LABOUR
0102 Blacksmith 1st class day 5 ₹897.00 ₹4,485.00
0114 Beldar day 5 ₹736.00 ₹3,680.00
9999 Sundries L.S. 126.1 ₹2.27 ₹286.25
0130 Mistry day 2.8 ₹897.00 ₹2,511.60
0102 Blacksmith 1st class day 8.4 ₹897.00 ₹7,534.80
0112 Carpenter 2nd class day 6.2 ₹816.00 ₹5,059.20
0114 Beldar day 16.8 ₹736.00 ₹12,364.80

Rate build-up

Total ₹1,27,132.27
Add 1 % Water charges on "W" ₹1,271.32
TOTAL ₹1,28,403.59
Add GST on "X" (multiplying factor 0.2127) ₹27,311.44
TOTAL ₹1,55,715.03
Add 15% CPOH on "Y" ₹23,357.25
TOTAL ₹1,79,072.28
Add Cess @ 1% on "Z" ₹1,790.72
Cost of 100 metre ₹1,80,863.00
Cost of 1 metre ₹1,808.63
Say ₹1,808.65