Providing & fixing false ceiling at all height including providing & fixing of framework made of special section, power pressed from M.S. sheets and galvanised with zinc coating of 120 gms/ sqm (both side inclusive) as per IS : 277 and consisting of angle cleat of size 25mm wide x 1.6mm thick with flanges of 27mm and 37mm, at 1200mm c/c, one flange fixed to the ceiling with dash fastener 12.5mm dia x 50mm long with 6mm dia bolts, other flange of cleat fixed to the angle hangers of 25 x10 x0.50mm of required length with nuts & bolts of required size and other end of angle hanger fixed with intermediate G.I chanels 45 x15 x 0.90mm running at the spacing of 1200 mm c/c, to which the ceiling section 0.5mm thick bottom wedge of 80mm with tapered flanges of 26 mm each having lips of 10.5mm, at 450mm c/c, shall be fixed in a direction perpendicular to G.I intermediate channel with connecting clip made out of 2.64mm dia x 230mm long G.I wire at every junction, including fixing perimeter channels 0.50mm thick 27mm high having flanges of 20mm and 30mm long, the perimeter of ceiling fixed to wall/ partitions with the help of Rawl plugs at 450mm centre, with 25mm long dry wall screws @ 230mm interval, including fixing of Calcium Silicate Board to ceiling section and perimeter channels with the help of dry wall screws of size 3.5 x25mm at 230mm c/c, including jointing & finishing to a flush finish of tapered and square edges of the board with recommended jointing compounds, jointing tapes,finishing with jointing compounds in three layers covering up to 150mm on both sides of joints and two coats of primer suitable for boards, all as per manufacture's specification and also including the cost of making opening for light fittings, grills, diffusers, cut outs made with frame of perimeter channels suitably fixed, all complete as per drawings, specificaton and direction of the Engineer in charge but excluding the cost of painting with: 8 mm thick Calcium Silicate Board made with Calcareous & Siliceous materials reinforced with cellulose fiber manufactured through autoclaving process.

Published rate₹1,572.30per sqm
Rate analysis

Providing & fixing false ceiling at all height including providing & fixing of framework made of special section, power pressed from M.S. sheets and galvanised with zinc coating of 120 gms/ sqm (both side inclusive) as per IS : 277 and consisting of angle cleat of size 25mm wide x 1.6mm thick with flanges of 27mm and 37mm, at 1200mm c/c, one flange fixed to the ceiling with dash fastener 12.5mm dia x 50mm long with 6mm dia bolts, other flange of cleat fixed to the angle hangers of 25 x10 x0.50mm of required length with nuts & bolts of required size and other end of angle hanger fixed with intermediate G.I chanels 45 x15 x 0.90mm running at the spacing of 1200 mm c/c, to which the ceiling section 0.5mm thick bottom wedge of 80mm with tapered flanges of 26 mm each having lips of 10.5mm, at 450mm c/c, shall be fixed in a direction perpendicular to G.I intermediate channel with connecting clip made out of 2.64mm dia x 230mm long G.I wire at every junction, including fixing perimeter channels 0.50mm thick 27mm high having flanges of 20mm and 30mm long, the perimeter of ceiling fixed to wall/ partitions with the help of Rawl plugs at 450mm centre, with 25mm long dry wall screws @ 230mm interval, including fixing of Calcium Silicate Board to ceiling section and perimeter channels with the help of dry wall screws of size 3.5 x25mm at 230mm c/c, including jointing & finishing to a flush finish of tapered and square edges of the board with recommended jointing compounds, jointing tapes,finishing with jointing compounds in three layers covering up to 150mm on both sides of joints and two coats of primer suitable for boards, all as per manufacture's specification and also including the cost of making opening for light fittings, grills, diffusers, cut outs made with frame of perimeter channels suitably fixed, all complete as per drawings, specificaton and direction of the Engineer in charge but excluding the cost of painting with:

DSR rate₹1,572.30per sqm

8 mm thick Calcium Silicate Board made with Calcareous & Siliceous materials reinforced with cellulose fiber manufactured through autoclaving process.

Item code
12.59.1
Sub-head
SH 12 · ROOFING
Unit
sqm
Source row
3325

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10.8 m x 9.6m = 103.68sqm
MATERIALS:
Area = 103.68 sq.m +
Add. Wastage of5% = 5.18 Sq.m Total =
108.86 Sqm
MATERIALS :
8699 8 mm thick tapered edge calcium silicate board sqm 108.86 ₹297.00 ₹32,331.42
7010 G.I Ceiling Section (80 x26mm x26mm x10.5mm each lip x 0.55 mm) metre 238.14 ₹49.00 ₹11,668.86
7011 Galvanised Steel perimetre Channel (Size 20x27x30x0.50mm) metre 41.84 ₹24.00 ₹1,004.16
7012 Galvanised Steel intermediate Channel (Size 15x45x15x0.90mm) metre 90.72 ₹40.00 ₹3,628.80
7013 Galvanised Steel angle hanger (Celling angle) (Size 25x10x0.50mm) metre 10.8 ₹13.00 ₹140.40
7014 Galvanised Steel connecting clips (2.64mm dia and 230 mm long GI wire) each 189 ₹4.00 ₹756.00
1022 Galvanised steel bolts & nuts 6 mm dia and 25 mmlong round head with slots 10 Nos 21.6 ₹38.00 ₹820.80
8617 Soffit cleat (Size 27x37x25x1.60mm) each 72 ₹6.00 ₹432.00
7020 All drive screws ( for gypsum board) 100 Nos 10 ₹63.00 ₹630.00
7016 Joint filler kilogram 22.81 ₹25.00 ₹570.25
7017 Joint finisher kilogram 34.21 ₹23.00 ₹786.83
7388 Dash hold fastener 12.5 mm dia, 40 mm
long with 6 mm dia bolt each 72 ₹10.00 ₹720.00
7018 Joint Tape roll (120mm Roll) roll 1.27 ₹95.00 ₹120.65
7021 Primer ( for gypsum board// calcium silicate board) litre 18.66 ₹75.00 ₹1,399.50
9977 Carriage L.S. 447.2 ₹2.27 ₹1,015.14
9999 Sundries i.e rawl plug, scaffolding etc. L.S. 807.3 ₹2.27 ₹1,832.57
LABOUR :
0112 Carpenter 2nd class day 31.1 ₹816.00 ₹25,377.60
0114 Beldar day 31.1 ₹736.00 ₹22,889.60
0131 Painter day 10.37 ₹816.00 ₹8,461.92

Rate build-up

TOTAL ₹1,14,586.50
Add 1 % Water charges on "W" ₹1,145.87
TOTAL ₹1,15,732.37
Add GST on "X" (multiplying factor 0.2127) ₹24,616.28
TOTAL ₹1,40,348.65
Add 15% CPOH on "Y" ₹21,052.30
TOTAL ₹1,61,400.95
Add Cess @ 1% on "Z" ₹1,614.01
Cost of 103.68 sqm. ₹1,63,014.96
Cost of 1 sqm. ₹1,572.29
Say ₹1,572.30