DSR 2023 · SH 12 · ROOFING

CPWD DSR item 12.54.1 rate analysis

Providing and fixing Gl Clip in Metal Ceiling System of 600x600 mm module which includes providing and fixing 'C' wall angle of size 20x30x20 mm made of 0.5 mm thick pre painted steel along the perimeter of the room with help of nylon sleeves and wooden screws at 300 mm center to centre, suspending the main C carrier of size 10x38x10 mm made of G.I steel 0.7 mm thick from the soffit with help of soffit cleat 37x27x25x1.6 mm, rawl plugs of size 38x12 mm and C carrier suspension clip and main carrier bracket at 1000 mm c/c. Inverted triangle shaped Spring Tee having height of 24 mm and width of 34 mm made of Gl steel 0.45 mm thick is then fixed to the main C carrier and in direction perpendicular to it at 600 mm centers with help of suspension brackets. Wherever the main C carrier and spring T have to join, C carrier and spring T connectors have to be used. All sections to be galvanized @ 120 gms/sqm (both side inclusive), fixing with clip in tiles into spring T with : GI Metal Ceiling Clip in plain Beveled edge global white color tiles of size 600x600 and 0.5 mm thick with 25 mm height, made of G I sheet having galvanizing of 100 gms/ sqm (both sides inclusive) and electro statically polyester powder coated of thickness 60 microns (minimum), including factory painted after bending.

Published rate₹2,221.70per sqm
Rate analysis

Providing and fixing Gl Clip in Metal Ceiling System of 600x600 mm module which includes providing and fixing 'C' wall angle of size 20x30x20 mm made of 0.5 mm thick pre painted steel along the perimeter of the room with help of nylon sleeves and wooden screws at 300 mm center to centre, suspending the main C carrier of size 10x38x10 mm made of G.I steel 0.7 mm thick from the soffit with help of soffit cleat 37x27x25x1.6 mm, rawl plugs of size 38x12 mm and C carrier suspension clip and main carrier bracket at 1000 mm c/c. Inverted triangle shaped Spring Tee having height of 24 mm and width of 34 mm made of Gl steel 0.45 mm thick is then fixed to the main C carrier and in direction perpendicular to it at 600 mm centers with help of suspension brackets. Wherever the main C carrier and spring T have to join, C carrier and spring T connectors have to be used. All sections to be galvanized @ 120 gms/sqm (both side inclusive), fixing with clip in tiles into spring T with :

DSR rate₹2,221.70per sqm

GI Metal Ceiling Clip in plain Beveled edge global white color tiles of size 600x600 and 0.5 mm thick with 25 mm height, made of G I sheet having galvanizing of 100 gms/ sqm (both sides inclusive) and electro statically polyester powder coated of thickness 60 microns (minimum), including factory painted after bending.

Item code
12.54.1
Sub-head
SH 12 · ROOFING
Unit
sqm
Source row
3122

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 100 sqm.
MATERIAL
Celling Area =100 sqm
Add wastage @ 5% = 5 sqm.
Total=105 sqm
8597 GI Metal Tile Clip in Plain Beveled edge global white colour tiles of size 600x600 mm and 0.5mm thick sqm 105 ₹793.00 ₹83,265.00
8604 Spring T-section 24x34x0.45 mm (3.00 meter long) metre 60 ₹240.00 ₹14,400.00
Including Wastage @ 10%
8605 C Wall angle section 20x30x20x0.50 mm (3.00 meter long) metre 27.7 ₹115.00 ₹3,185.50
Including Wastage @ 10%
8606 Main C Carrier Size 10x38x10x0.70mm (3.00 meter long) metre 33 ₹135.00 ₹4,455.00
Including Wastage @ 10% on Grid for cut outs
8607 Spring T-connector each 44 ₹6.00 ₹264.00
8608 C Carrier Connector each 44 ₹13.00 ₹572.00
8609 C Suspension Clip each 88 ₹11.00 ₹968.00
8610 Wire Coupling Clip each 333 ₹11.00 ₹3,663.00
8615 Hanger rod 4 mm thick each 80 ₹11.00 ₹880.00
8616 Adjustment clip 85x30x0.8mm each 80 ₹7.00 ₹560.00
8617 Soffit cleat (Size 27x37x25x1.60mm) each 80 ₹6.00 ₹480.00
7388 Dash hold fastener 12.5 mm dia, 40 mm long with 6 mm dia bolt each 80 ₹10.00 ₹800.00
9999 Sundries i.e. scaffolding etc. L.S. 188 ₹2.27 ₹426.76
9977 Carriage of materials etc. L.S. 90 ₹2.27 ₹204.30
LABOUR
0111 Carpenter 1st class day 28 ₹897.00 ₹25,116.00
0114 Beldar day 23 ₹736.00 ₹16,928.00

Rate build-up

TOTAL ₹1,56,167.56
Add 1 % Water charges on "W" ₹1,561.68
TOTAL ₹1,57,729.24
Add GST on "X" (multiplying factor 0.2127) ₹33,549.01
TOTAL ₹1,91,278.25
Add 15% CPOH on "Y" ₹28,691.74
TOTAL ₹2,19,969.99
Add Cess @ 1% on "Z" ₹2,199.70
Cost of 100 sqm. ₹2,22,169.69
Cost of 1 sqm. ₹2,221.70
Say ₹2,221.70

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook