DSR 2023 · SH 12 · ROOFING

CPWD DSR item 12.49 rate analysis

Providing & laying on roof pressed clay tile ridge (Mangalore tile) of 20mm thickness and of approved pattern on steel frame work complete (steel frame work to be paid separately).

Published rate₹96.90DSR 2023
Rate analysis

Providing & laying on roof pressed clay tile ridge (Mangalore tile) of 20mm thickness and of approved pattern on steel frame work complete (steel frame work to be paid separately).

DSR rate₹96.90as per item analysis
Item code
12.49
Sub-head
SH 12 · ROOFING
Unit
See analysis
Source row
2716

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 3.60 metre
MATERIAL
8669 Mangalore ridge tiles 20 mm thick each 12 ₹10.00 ₹120.00
2207 Carriage of Brick tiles 1000 Nos 0.012 ₹0.00 ₹0.00
LABOUR
0123 Mason 1st class day 0.01 ₹897.00 ₹8.97
0114 Beldar day 0.15 ₹736.00 ₹110.40
9999 Sundries L.S. 2.6 ₹2.27 ₹5.90

Rate build-up

TOTAL ₹245.27
Add 1 % Water charges on "W" ₹2.45
TOTAL ₹247.72
Add GST on "X" (multiplying factor 0.2127) ₹52.69
TOTAL ₹300.41
Add 15% CPOH on "Y" ₹45.06
TOTAL ₹345.47
Add Cess @ 1% on "Z" ₹3.45
Cost of 3.60 metre ₹348.92
Cost for 1 metre ₹96.92
Say ₹96.90

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook