Rate analysis
Providing and fixing M.S. holder bat clamps of approved design to C.I. or S.C.I. rain water pipes embedded in and including cement concrete blocks 10x10x10 cm of 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and cost of cutting holes and making good the walls etc. :
DSR rate₹362.85as per item analysis
100 mm diameter
- Item code
- 12.38.1
- Sub-head
- SH 12 · ROOFING
- Unit
- See analysis
- Source row
- 1954
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost of 50 nos. | |||||
| MATERIAL | |||||
| 1331 | M.S.Holder bat clamp of approved design for 100 mm S.C.I. pipe | each | 50 | ₹27.00 | ₹1,350.00 |
| C.C. block 50x0.1x0.1x0.1 = 0.05 cum | |||||
| 9977 | Carriage of bat clamps | L.S. | 24.7 | ₹2.27 | ₹56.07 |
| 9999 | Sundries | L.S. | 71.5 | ₹2.27 | ₹162.31 |
| LABOUR | |||||
| 0116 | Fitter (grade 1) | day | 1.25 | ₹897.00 | ₹1,121.25 |
| 0124 | Mason 2nd class | day | 7.5 | ₹816.00 | ₹6,120.00 |
| 0114 | Beldar | day | 5 | ₹736.00 | ₹3,680.00 |
| 0295 | Stone Aggregate (Single size) : 20 mm nominal size | cum | 0.033 | ₹1,425.00 | ₹47.03 |
| 0297 | Stone Aggregate (Single size) : 10 mm nominal size | cum | 0.011 | ₹1,400.00 | ₹15.40 |
| 2202 | Carriage of Stone aggregate below 40 mm nominal size | cum | 0.044 | ₹0.00 | ₹0.00 |
| 0982 | Coarse sand (zone III) | cum | 0.022 | ₹1,450.00 | ₹31.90 |
| 2203 | Carriage of Coarse sand | cum | 0.022 | ₹0.00 | ₹0.00 |
| 0367 | Portland Cement (OPC-43 grade) | tonne | 0.016 | ₹5,156.00 | ₹82.50 |
| 2209 | Carriage of Cement | tonne | 0.016 | ₹0.00 | ₹0.00 |
| 0114 | Beldar | day | 0.045 | ₹736.00 | ₹33.12 |
| 0115 | Coolie | day | 0.032 | ₹736.00 | ₹23.55 |
| 0101 | Bhisti | day | 0.014 | ₹816.00 | ₹11.42 |
| 0123 | Mason 1st class | day | 0.003 | ₹897.00 | ₹2.69 |
| 0124 | Mason 2nd class | day | 0.003 | ₹816.00 | ₹2.45 |
| 0128 | Mate | day | 0.002 | ₹816.00 | ₹1.63 |
| 9999 | Hire charges of machine etc. | L.S. | 2.6 | ₹2.27 | ₹5.90 |
| 9999 | Sundries | L.S. | 1.3 | ₹2.27 | ₹2.95 |
| 9999 | Sundries | L.S. | 1.3 | ₹2.27 | ₹2.95 |
Rate build-up
| TOTAL | ₹12,753.12 |
| Add 1 % Water charges on "W" | ₹127.53 |
| TOTAL | ₹12,880.65 |
| Add GST on "X" (multiplying factor 0.2127) | ₹2,739.71 |
| TOTAL | ₹15,620.36 |
| Add 15% CPOH on "Y" | ₹2,343.05 |
| TOTAL | ₹17,963.41 |
| Add Cess @ 1% on "Z" | ₹179.63 |
| Cost of 50 bat clamps | ₹18,143.04 |
| Cost of 1.00 bat clamp | ₹362.86 |