DSR 2023 · SH 12 · ROOFING

CPWD DSR item 12.33 rate analysis

Extra for providing plaster of Paris (Gypsum anhydrous) ceiling above 5 metres height from floor level.

Published rate₹265.70DSR 2023
Rate analysis

Extra for providing plaster of Paris (Gypsum anhydrous) ceiling above 5 metres height from floor level.

DSR rate₹265.70as per item analysis
Item code
12.33
Sub-head
SH 12 · ROOFING
Unit
See analysis
Source row
1812

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10sqm/metre height
9999 Scaffolding L.S. 13.52 ₹2.27 ₹30.69
LABOUR
0122 Mason (for plaster of paris work) 1st class day 1 ₹897.00 ₹897.00
0114 Beldar day 1 ₹736.00 ₹736.00
0101 Bhisti day 0.25 ₹816.00 ₹204.00

Rate build-up

TOTAL ₹1,867.69
Add 1 % Water charges on "W" ₹18.68
TOTAL ₹1,886.37
Add GST on "X" (multiplying factor 0.2127) ₹401.23
TOTAL ₹2,287.60
Add 15% CPOH on "Y" ₹343.14
TOTAL ₹2,630.74
Add Cess @ 1% on "Z" ₹26.31
Cost of 10.00sqm / metre height ₹2,657.05
Cost of 1.00 sqm. / metre height ₹265.71
Say ₹265.70

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook