DSR 2023 · SH 12 · ROOFING

CPWD DSR item 12.31.1 rate analysis

Providing 10 mm thick plaster of Paris (gypsum anhydrous) ceiling up to a height of 5 m above floor level, over first class kail wood strips 25x6 mm with 10 mm gap in between and reinforced with rabbit wire mesh fixed to wooden frame (frame work to be paid separately): Flat surfaces

Published rate₹1,718.95DSR 2023
Rate analysis

Providing 10 mm thick plaster of Paris (gypsum anhydrous) ceiling up to a height of 5 m above floor level, over first class kail wood strips 25x6 mm with 10 mm gap in between and reinforced with rabbit wire mesh fixed to wooden frame (frame work to be paid separately):

DSR rate₹1,718.95as per item analysis

Flat surfaces

Item code
12.31.1
Sub-head
SH 12 · ROOFING
Unit
See analysis
Source row
1696

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10x4.00x2.5=100sqm.
MATERIAL
Wooden strips of 1st class kail wood 10x72x40x0.25x0.06 = 432 cudm. +
Add 10% wastage = 43.2 cudm.
Total = 475.2 cudm
1196 First class kail wood in planks 10 cudm 47.52 ₹300.00 ₹14,256.00
2204 Carriage of Timber cum 0.475 ₹0.00 ₹0.00
1219 Wire nails kilogram 7.5 ₹58.00 ₹435.00
required for fixing the laths to frame work including breakage and wastage of nails
Rabbit wire mesh required for reinforcement =10x2.5x4 = 100sqm.+
Add 2% wastage = 2 sqm.
Total = 102 sqm.
1220 Wire mesh (rabbit) sqm 102 ₹42.00 ₹4,284.00
Plaster of paris - 10x2.5x4.0x10x1121/1000 = 1121 kg.
Add for plaster of paris joining into the
side of the laths- 10x2.5x4.0x4.0032x1121/1000 = 448.7 kg.
Total = 1569.7+
Add 40% wastage = 627.9
Total = 2197.6 kg
0869 Plaster of Paris kilogram 2,197.6 ₹7.00 ₹15,383.20
2308 Carriage of Plaster of paris tonne 2.2 ₹0.00 ₹0.00
9977 Carriage of wiremesh and nails etc. L.S. 27.3 ₹2.27 ₹61.97
LABOUR
0111 Carpenter 1st class day 16 ₹897.00 ₹14,352.00
0114 Beldar day 16 ₹736.00 ₹11,776.00
For doing plaster of paris over wooden strips
0122 Mason (for plaster of paris work) 1st class day 32.3 ₹897.00 ₹28,973.10
0114 Beldar day 32.3 ₹736.00 ₹23,772.80
0101 Bhisti day 5.4 ₹816.00 ₹4,406.40
9999 Scaffolding L.S. 839.8 ₹2.27 ₹1,906.35
9999 Sundries L.S. 538.2 ₹2.27 ₹1,221.71

Rate build-up

TOTAL ₹1,20,828.53
Add 1 % Water charges on "W" ₹1,208.29
TOTAL ₹1,22,036.82
Add GST on "X" (multiplying factor 0.2127) ₹25,957.23
TOTAL ₹1,47,994.05
Add 15% CPOH on "Y" ₹22,199.11
TOTAL ₹1,70,193.16
Add Cess @ 1% on "Z" ₹1,701.93
Cost of 100 sqm. ₹1,71,895.09
Cost of 1.00 sqm. ₹1,718.95
Say ₹1,718.95

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook