Rate analysis
Extra for straight cutting in C.G.S. sheet roofing for making opening of area exceeding 40 sq. decimeter for chimney stacks, sky light etc.:
DSR rate₹92.95as per item analysis
0.80 mm thick
- Item code
- 12.2.2
- Sub-head
- SH 12 · ROOFING
- Unit
- See analysis
- Source row
- 200
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 3 metres periphery | |||||
| Assuming a hole of 10dmx5dm area of the hole 50dm2 and the perimeter of the hole 3 metre | |||||
| LABOUR | |||||
| 0102 | Blacksmith 1st class | day | 0.12 | ₹897.00 | ₹107.64 |
| 0114 | Beldar | day | 0.12 | ₹736.00 | ₹88.32 |
Rate build-up
| TOTAL | ₹195.96 |
| Add 1 % Water charges on "W" | ₹1.96 |
| TOTAL | ₹197.92 |
| Add GST on "X" (multiplying factor 0.2127) | ₹42.10 |
| TOTAL | ₹240.02 |
| Add 15% CPOH on "Y" | ₹36.00 |
| TOTAL | ₹276.02 |
| Add Cess @ 1% on "Z" | ₹2.76 |
| Cost of 3.00 metres | ₹278.78 |
| Cost of 1.00 metre | ₹92.93 |
| Say | ₹92.95 |