Rate analysis
Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete:
DSR rate₹303.70as per item analysis
Ridge finials
- Item code
- 12.13.6
- Sub-head
- SH 12 · ROOFING
- Unit
- See analysis
- Source row
- 747
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of a pair of ridge final | |||||
| MATERIAL | |||||
| Ride final = pair | |||||
| Add 5% wastage = 0.05pair. | |||||
| Total = 1.05 pair | |||||
| 0233 | Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement ridge finial . | pair | 1.05 | ₹180.00 | ₹189.00 |
| 9988 | Carriage, sundries, fixing charges including providing and fixing, seam bolts and nuts, with G.I. and bitumen washers | L.S. | 10.79 | ₹2.27 | ₹24.49 |
Rate build-up
| TOTAL | ₹213.49 |
| Add 1 % Water charges on "W" | ₹2.13 |
| TOTAL | ₹215.62 |
| Add GST on "X" (multiplying factor 0.2127) | ₹45.86 |
| TOTAL | ₹261.48 |
| Add 15% CPOH on "Y" | ₹39.22 |
| TOTAL | ₹300.70 |
| Add Cess @ 1% on "Z" | ₹3.01 |
| Cost of 1.00 pair | ₹303.71 |
| Say | ₹303.70 |