DSR 2023 · SH 12 · ROOFING

CPWD DSR item 12.1 rate analysis

Extra for circular cutting in reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated/ semi corrugated 6 mm thick sheet roofing for making openings of area exceeding 40 square decimeter.

Published rate₹256.70DSR 2023
Rate analysis

Extra for circular cutting in reinforced by organic fibres and/or inorganic synthetic fibres cement corrugated/ semi corrugated 6 mm thick sheet roofing for making openings of area exceeding 40 square decimeter.

DSR rate₹256.70as per item analysis
Item code
12.1
Sub-head
SH 12 · ROOFING
Unit
See analysis
Source row
590

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 4 holes of 0.72 metre diameter i.e. 9.05 metre periphery
LABOUR
0111 Carpenter 1st class day 1 ₹897.00 ₹897.00
0114 Beldar day 1 ₹736.00 ₹736.00

Rate build-up

TOTAL ₹1,633.00
Add 1 % Water charges on "W" ₹16.33
TOTAL ₹1,649.33
Add GST on "X" (multiplying factor 0.2127) ₹350.81
TOTAL ₹2,000.14
Add 15% CPOH on "Y" ₹300.02
TOTAL ₹2,300.16
Add Cess @ 1% on "Z" ₹23.00
Cost of 9.05 metres of periphery ₹2,323.16
Cost of 1.00 metre of periphery ₹256.70
Say ₹256.70

Use this rate in the interactive workbook