Rate analysis
40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement mortar 1:5 (1 cement : 5 coarse sand), including pointing with cement mortar 1:2 (1 cement : 2 stone dust) with an admixture of pigment to match the shade of stone.
DSR rate₹1,526.05as per item analysis
Red sand stone
- Item code
- 11.29.1
- Sub-head
- SH 11 · FLOORING
- Unit
- See analysis
- Source row
- 2107
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10sqm. | |||||
| MATERIAL | |||||
| Finished work = 10 sqm | |||||
| Add for wastage @ 10% = 1 sqm | |||||
| Total = 11 sqm | |||||
| 1164 | Red sand stone slab 40 mmthick (un-dressed) | sqm | 11 | ₹330.00 | ₹3,630.00 |
| 9977 | Carriage | L.S. | 34.06 | ₹2.27 | ₹77.32 |
| Cement mortar 1 : 5 (1 cement : 5 coarse sand) | |||||
| (i) for beading = 0.224 cum+ | |||||
| (ii) for joining = 0.026 cum. | |||||
| Total=0.250cum. | |||||
| 3.1 | Rate as per Item Number 3.10 of SH: Mortars | cum | 0.25 | ₹3,850.75 | ₹962.69 |
| Cement mortar 1:2 (1 Cement : 2 stone dust for pointing) | |||||
| 3.12 | Rate as per Item Number 3.12 of SH: Mortars | cum | 0.023 | ₹5,252.00 | ₹120.80 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 3.9 | ₹897.00 | ₹3,498.30 |
| 0100 | Bandhani | day | 1.1 | ₹816.00 | ₹897.60 |
| 0115 | Coolie | day | 1.4 | ₹736.00 | ₹1,030.40 |
| 0101 | Bhisti | day | 0.55 | ₹816.00 | ₹448.80 |
| 9999 | Sundries | L.S. | 26.91 | ₹2.27 | ₹61.09 |
Rate build-up
| TOTAL | ₹10,727.00 |
| Add 1 % Water charges on "W" | ₹107.27 |
| TOTAL | ₹10,834.27 |
| Add GST on "X" (multiplying factor 0.2127) | ₹2,304.45 |
| TOTAL | ₹13,138.72 |
| Add 15% CPOH on "Y" | ₹1,970.81 |
| TOTAL | ₹15,109.53 |
| Add Cess @ 1% on "Z" | ₹151.10 |
| Cost for 10sqm. | ₹15,260.63 |
| Cost for 1sqm. | ₹1,526.06 |
| Say | ₹1,526.05 |