DSR 2023 · SH 11 · FLOORING

CPWD DSR item 11.17 rate analysis

Extra if terrazo tiles are laid in treads of steps not exceeding 30 cm in width.

Published rate₹124.05per sqm
Rate analysis

Extra if terrazo tiles are laid in treads of steps not exceeding 30 cm in width.

DSR rate₹124.05per sqm
Item code
11.17
Sub-head
SH 11 · FLOORING
Unit
sqm
Source row
1202

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 sqm.
LABOUR
0124 Mason 2nd class day 0.22 ₹816.00 ₹179.52
0115 Coolie day 0.22 ₹736.00 ₹161.92
0139 Skilled Beldar (for floor rubbing etc.) day 0.65 ₹816.00 ₹530.40

Rate build-up

TOTAL ₹871.84
Add 1 % Water charges on "W" ₹8.72
TOTAL ₹880.56
Add GST on "X" (multiplying factor 0.2127) ₹187.30
TOTAL ₹1,067.86
Add 15% CPOH on "Y" ₹160.18
TOTAL ₹1,228.04
Add Cess @ 1% on "Z" ₹12.28
Cost of 10 sqm. ₹1,240.32
Cost of 1 sqm. ₹124.03
Say ₹124.05

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook