CPWD DSR item 11.12.1.5 rate analysis

Marble chips skirting up to 30 cm height, rubbed and polished to granolithic finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from smallest to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume : 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement : 3 coarse sand) : Light shade pigment with ordinary cement

Published rate₹1,860.25per sqm
Rate analysis

Marble chips skirting up to 30 cm height, rubbed and polished to granolithic finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or green marble chips of sizes from smallest to 4 mm nominal size, laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volume : 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement : 3 coarse sand) :

DSR rate₹1,860.25per sqm

Light shade pigment with ordinary cement

Item code
11.12.1.5
Sub-head
SH 11 · FLOORING
Unit
sqm
Source row
811

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 sqm
11.12.1.1 Rate as per Item Number 11.12.1.1 of SH: Flooring sqm 10 ₹1,864.30 ₹18,643.00
Add difference of cost due to using Light shade pigment instead of dark shade pigment
Add for
0875 Red, chocolate, orange, buff or yellow (red oxide of iron) light shade pigment kilogram 2.84 ₹65.00 ₹184.60
Deduct for
0874 Black colour dark shade pigment kilogram -2.84 ₹75.00 -₹213.00

Rate build-up

TOTAL ₹18,614.60
Add 1 % Water charges on "W-A" -₹0.28
TOTAL ₹18,614.32
Add GST on "X-A" (multiplying factor 0.2127) -₹6.10
TOTAL ₹18,608.22
Add 15% CPOH on "Y-A" -₹5.22
TOTAL ₹18,603.00
Add Cess @ 1% on "Z-A" -₹0.40
Cost of 10 sqm. ₹18,602.60
Cost of 1 sqm. ₹1,860.26
Say ₹1,860.25