DSR 2023 · SH 1

CPWD DSR item 1.4.3 rate analysis

Loading in or unloading from the railway wagons as per direction of Engineer-in-charge : Heavy materials where each piece or bundle, crate or case weighs more than one tonne and R.C.C., C.I. and concrete pipes above 500 mm dia.

Published rate₹263.15per tonne
Rate analysis

Loading in or unloading from the railway wagons as per direction of Engineer-in-charge :

DSR rate₹263.15per tonne

Heavy materials where each piece or bundle, crate or case weighs more than one tonne and R.C.C., C.I. and concrete pipes above 500 mm dia.

Item code
1.4.3
Sub-head
SH 1
Unit
tonne
Source row
18

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost of unloading wagon of 14 tonnes
LABOUR
0114 Beldar day 3.25 ₹736.00 ₹2,392.00
9999 Extra for fixing crane including labour involved L.S. 91.15 ₹2.27 ₹206.91
9999 Sundries L.S. 7.4 ₹2.27 ₹16.80

Rate build-up

TOTAL ₹2,615.71
Add GST on "X" (multiplying factor 0.2127) ₹556.36
TOTAL ₹3,172.07
Add 15% CPOH on "Y" ₹475.81
TOTAL ₹3,647.88
Add Cess @ 1% on "Z" ₹36.48
Cost of 14 tonne ₹3,684.36
Cost of 1 tonne ₹263.17
Say ₹263.15

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook